The link http://www.rvnl.org/project/project_desc.php?id=74 has the following.

 NAME OF THE PROJECT–    BURAMARA – CHAKULIA – NEW LINE WITH UPGRADING OF RUPSA – BURAMARA
   
Plan Head NEW LINE PIU CPM KOLKATA
Rly. SOUTH EASTERN Executing Agency RVNL
State ORISSA Funding Source SPV
Length (Kms) 125.00 Status Under Development Stage.
GQ/PC PC Anticipated Cost (Cr.) 466.48

This is the latest addition to the list of RVNL projects. (15 of 60 projects in that list involve Orissa.)  It is listed as a port connectivity (PC) project. Among the various proposed ports in that area, Dhamra port is closest to be operational. This link will shorten Rupsa-Chakulia distance from 167 kms to 125 kms. More importantly it will bypass the busy Kharagpur junction and provide an alternative path to Tatanagar. It will also provide a bypass of the area that sometimes gets flooded by the Subarnarekha river.


The following map illustrates the area. (Thanks to Samit for permitting to use this map fragment from his book.)

The following is from SER’s Kharagpur division map.


 


The complete list of 15 Orissa related projects listed at http://www.rvnl.org/project/project.php are: 

  1. (11) KHARAGPUR (NIMPURA) – BHUBANESWAR (GQ electrification – completed)
  2. (12) BHUBANESWAR – KOTTAVALASA ELECT (GQ electrification – completed)
  3. (14) TALCHAR-CUTTACK-PARADEEP DOUBLING WITH 2ND BRIDGE ON RIVERS BIRUPA AND MAHANADI (GQ doubling completed)
  4. (15) DAITARI – BANSPANI NEW LINE (Port connectivity completed)
  5. (19) ANGUL – SUKINDA NEW LINE (Post connectivity – under development)
  6. (20) JAKHPURA- HARIDASPUR 3RD LINE DOUBLING (Port connectivity – recently sanctioned)
  7. (26) RAJATGARH – BARANG DOUBLING (GQ – work in progress)
  8. (27) CUTTACK – BARANG DOUBLING (GQ – work in progress)
  9. (28) KHURDA ROAD – BARANG 3RD LINE DOUBLING (GQ – work in progress)
  10. (44) HARIDASPUR – PARADEEP NEW LINE (Port connectivity – work in progress)
  11. (53) TOMKA -BANASPANI – RE (Port connectivity, electrification, recently sanctioned)
  12. (54) SAMBALPUR – TITLAGARH – DOUBLING (Port connectivity, recently sanctioned)
  13. (55) RAIPUR – TITLAGARH – DOUBLING (Port connectivity, recently sanctioned)
  14. (60) BANASPANI – JAKHPURA – DOUBLING (Port connectivity, electrification, unsanctioned)
  15. (63) BURAMARA – CHAKULIA – NEW LINE WITH UPGRADING OF RUPSA – BURAMARA (port connectivity, new line, under development)

 With the Gopalpur port getting ready, RVNL should be soon taking up the Gunupur-Theruvali line.