L & T to execute NISER Bhubaneswar construction; work to start next month and be completed in 36 months

Following are excerpts from Bibhuti Barik’s report in Telegraph.

… The master plan is ready and the Department of Atomic Energy (DAE) has selected Larsen and Toubro (L&T) to execute the job. They are expected to start the work next month. The project has to be completed within 36 months … We hope that the Phase-I work comprising four major schools and the administrative block will be over by the end of 2013,’’ said the institute’s registrar, AK Naik.

The campus is coming up on 298 acres near Jatni.

While the forest department has already marked 285 trees for felling top facilitate work, steps to ensure enough greenery are being taken by planting 2,500 saplings along its fenced boundary. “We are planning more afforestation programmes in future,” added Naik.

The project envisages an expenditure of Rs 457 crore in the first phase including Rs 160 core on residential township and Rs 130 crore on academic buildings and a sports complex. The Centre has sanctioned Rs 823.19 core for the entire campus project in Bhubaneswar.

After fencing the authorities have deployed a 25-member security team with a supervising officer to keep watch. … the NISER campus site is safe. A transformer has been installed at the site to ensure uninterrupted power supply. Two corrugated tin sheds have also been put up at the site for the engineers to work out of.

The Registrar added that the construction work was getting delayed as the approval of the one of a senior officials of the Ministry of Finance was still awaited. Once it was available the executing agency would go ahead with the work. Earlier there was some delay on account of the time taken by the department of atomic energy (DAE) to grant certain approvals.

“The DAE technical panel inspected, checked and approved each and every aspect of the engineering drawing which took one year,” said a senior professor, who is an advisor and member on the NISER Board.

Currently operating from a transit campus of 5,000 square metres within the Institute of Physics (IoP), Bhubaneswar premises, NISER has lab, teaching and research facilities. While Rs 12.5 crore has been spent on these facilities for the school of chemistry Rs 13.5 crore for the school of physics, Rs 25 crore for the school of biology and Rs 5 crore for the school of mathematics.

… “We have been promised a three-acre plot by the state government for setting up a city campus in future. This will include a 1,500 seated conference hall,” said the registrar.