Vedanta a role model for other industries in Orissa; hope Jindal and others learn from it
Anil Agarwal, High Court, Jindal, Thermal, TOI, Economic Times July 9th. 2009, 11:58amNote: There are often many PR related activities by Vedanta and we usually don’t cover them. But this is an exceptional act of good citizenship on the part of Vedanta when the state is going through an extremely difficult time with respect to its power situation. The excerpts below are from an article by journalist Nageswar Patnaik, who is often very critical of industrial houses. Coming from him, this reinforces the genuineness and the importance of this good action by Vedanta and thus needs to be highlighted.
This should be contrasted with the Jindal group, which was reported to have violated the agreement it signed with Orissa government, and siphoned off extra power, until it was stopped by the high court.
Vedanta Group has finally come to the rescue of Orissa which is currently facing an acute power shortage due to scanty rainfall and "almost dried-up" reservoirs and breakdown of certain thermal power units in the state.
The London-based company on Thursday announced to provide 200 MW power daily to the state grid from its own power plants with immediate effect.
Vedanta has managed to get a better price for offloading power to the grid at the rate of Rs 3.60 per unit against the current Rs 3 per unit bought by the state from the CPPs.
In fact, Vedanta had been providing 115 MW of power from its Group Company BALCO in Chattisgarh to Orissa since July 4 by depriving its own smelter.
"Looking at the continuous demand in the state, Vedanta extended its supply with effect from July 9 from Jharsuguda and has managed to provide additional 100 MW of power to the state grid. The total capacity provided by Vedanta will cover up to the tune of one third of overall power shortage in the state," a source in the company said.
This was accomplished in the face of severe challenges, including shortage of coal and non availability of railway "rack," Mr Siddiqi said, assuring, to stand solidly behind the state in all its critical times.
On an average, Orissa’s daily requirement is around 2400 MW, which goes up to 2,800 to 3,000 MW during the peak hours in the evening. The state has a combined installed capacity from hydel projects to the tune of 1,900 MW. But they are generating around 1,000 MW.
Orissa is passing through power crisis forcing the authorities to restrict load restriction on industrial users by 50% among other measures to tackle the situation.
The state is facing shortage of power by 300 MW on an average and 450 to 500 MW at peak time. The delayed monsoon made things worse while the breakdown in the coal fired power plants operating in the state added to the crisis.
The VAL has set up a Greenfield alumina refinery in Orissa’s Kalahandi district with a capacity of 1 million tons per annum. It is also setting up a 0.5 MTPA aluminum smelter, 1215 MW captive power plant at Jharsuguda.
The Group Company Sterlite Energy Limited is also setting up a 2400 MW Independent Power Plants at Jharsuguda.