The face book page is at http://www.facebook.com/home.php?#!/Tatasteelparivar. Following are some updates from that page.

  • July 10, 1:19 AM: Construction at Site – The construction work at the main plant site will start shortly after the rehabilitation and resettlement process is completed. But other construction work to support the main plant like Intake Well, IM Section, Fabrication Yard, Hospital and most importantly the rehabilitation colonies and camps have already started.
  • July 10, 1:22 AM
  • July 12, 12:55 AM: Plant Equipments – Orders worth Rs 6,373 crore for the equipment and civil structures have already been placed. While the equipments like Blast Furnace and Sinter Plant for the steel plant have already been received and stored in the Tata Growth Shop and Agrico at Jamshedpur and Bamnipal, the orders for Steel Melting Shop and Coke Oven have been placed.
  • July 12, 12:58 AM: Civil Structural Work – Orders of more than 1,000 crore for civil structural work has been placed.
  • 12:59 AM: Intake Well – The intake well is located at Marthapur on the bank of river Brahmani, situated about 18 kms from the main plant site. This intake well will supply water to the plant.
  • 1:00 AM: Fabrication Yard – The steel structures required for construction of different shops like steel melting shop, blast furnace etc are being fabricated at the Fabrication Yad at Jodabar. About 2200 MT of steel have already been fabricated at this unit. The members of Tata Steel Paribar after being trained are also working here.
  • 11:42 PM: I M Section – The Company is constructing two covered sheds near Duburi to store the plant and machineries required for the construction of steel plant.
  • 11:44 PM: Hospital – To extend better healthcare facilities to the people in and around Kalinga Nagar, Tata Steel is setting-up a hospital in Gobarghati rehabilitation colony. The hospital building is under construction on a land of 4 acres. When completed this hospital would serve 10,000 families with round-the-clock service, pathology lab and outdoor complex.
  • 11:44 PM: Construction at the rehabilitation and resettlement Colonies – Tata Steel has developed three rehabilitation and resettlement colonies as well as five transit camps at Kalinga Nagar to ensure smooth living of the relocated families.
  • 11:45 PM: Power to the Main Plant Site:- The Steel Plant at Orissa is a complex combination of Steel Processing technologies designed at much larger scale to improve efficiency and therefore have large demand on stability & control on operating areas including the Power generation & Distribution system.
  • 11:45 PM: The plant has been designed with three separate sources to pull in Power and increase the tolerance of the system to handle large Power requirement of Steel Plant and with only GRID source during Construction
  • 11:45 PM: The captive Power plant inside the Kalinganagar plant area fuelled by the By-product gases generated by the steel making process (CPP by Tata Power)
  • 11:46 PM: Orissa Grid from 220 kV New Duburi GSSII Sub Station.
  • 11:46 PM: Captive Coal based Power plant at Naraj Marthapur (CPP by Tata Power)
  • July 13, 5:00 AM: Tata Steel Rural Development Society (TSRDS)a non-profit organisation has been trying to bring the displaced tribal communities of Jajpur District in Orissa to the mainstream through their socio-economic development. TSRDS has helped the tribal men and women from the displaced families in health care, safe drinking water, sanitation, women empowerment, livelihood etc.
  • July 14, 2:04 AM: Logistics – The life line of a steel plant is its logistics. It is a well known fact that every single ton of steel production needs transportation of minimum 4 ton of raw material and finished goods. So right from location selection to layout design, logistics plays a vital role in planning a new mega steel plant like the Kalinganagar Steel plant in Jajpur’ Orissa.
  • 2:05 AM: Iron ore, coal (Domestic as well as imported) and imported limestone are the prime inputs for the steel plant. The Iron ore mines and main port of relevance i.e. Dhamra Port, is barely 100 KM from the plant site. For Orissa Steel Project all these sources are connected via rail linkages. Some through existing Indian Rail network and some portion is planned under captive Logistic projects.
  • 2:05 AM:  RITES had been appointed as the consultant to prepare the detail rail plan which consists of (a) The Traffic projection & Capacity calculation for the existing IR network (b) Rail alignment and Take off plan for Tata Steel’s Sidings. (c) Cost estimate of the total Project.
  • 2:06 AM:  Apart from the plant internal rail yards Orissa Project, will require a 25 KM (Route Length) captive rail connection in Mines and a 20 KM (Route length) rail connection for plant connectivity to the nearest serving rail stations (Baghuapal & Jakhapura).
  • 2:06 AM: These have been designed considering the highest operating efficiency level and zero process interruption probability. Railway Board and Zonal railway have finally accepted our comprehensive rail logistic proposal.
  • 2:57 AM: At Integrated Industrial Complex, Kalinga Nagar, Duburi, in the district of Jajpur, in Odisha, a 6 million tonnes integrated steel plant of Tata Steel is proposed to be setup. Setting up the steel plant will necessitate displacement of about 679 families of three villages, namely, Gobaraghati, Chandia and Gadapur. Tata Steel has already started providing state of the art training for the members of the displaced families and would provide employment to one member of each extended family.Tata Steel is building model rehabilitation colonies for the resettlement of the displaced population so as to provide modern basic amenities and improved living conditions.Tata Steel believes that the primary purpose of the business is to improve the quality of life of people. Each of the displaced families will be a part of the ‘Tata Steel Parivar’ which is a committed and structured approach to ensure a better quality of life for the displaced families through focused interventions.
  • July 15:  Apart from the plant internal rail yards Orissa Project, will require a 25 KM (Route Length) captive rail connection in Mines and a 20 KM (Route length) rail connection for plant connectivity to the nearest serving rail stations (Baghuapal & Jakhapura).
  • These have been designed considering the highest operating efficiency level and zero process interruption probability. Railway Board and Zonal railway have finally accepted our comprehensive rail logistic proposal.
  • Although the bulk of the Material movement for an operating steel plant is done via rail transport for all the external movement and through conveyor system for in-plant movements.
  • But road transport also plays a vital role in the operating logistics of a steel plant, due to the fact that, there is no economical means of transporting a wide variety of materials required for or generated from the operation of process plants, which needs transportation in small quantity for a short distance.
  • In addition, a significant portion of the finished goods movement is required to be transported by road vehicles only.
  • But Unlike Jamshedpur, fortunately Kalinganagar industrial area is well-connected by road. Our Plant site is flanked by Daitari- Paradip express way which got converted to NH-200 recently and on the eastern side, the state highway connects the Sukinda Mines, to our plant site.
  • A road transport planning for a steel plant includes building roadways and plant roads , parking stations, maintenance facilities, service roads, a transport circulation plan and a scientific traffic projection. All these have been done with the help of a professional organization.