Status of doubling based on the 2011-12 railway budget
Doubling, ECOR, Railway Budget 2008, Railway Budget 2009, Railway Budget 2010, Railway Budget 2011 March 5th. 2011, 4:21pmBased on the 2011-12 and 2010-11 budgets the status of doubling in Odisha is as follows:
- Second bridge over Mahanadi and Birupa: Done.
- Nergundi-Rajathgarh-Barang: Nergundi-Rajathgarh is basically done. For Rajathgarh-Barang, this year there is an allocation of 33.2 Crores. With this allocation, by March 2012, 265.2 crores is expected to be spent. This is out of a total estimated budget of 275 crores. In other words by 2012 March this part will be almost done.
- Nergundi-Cuttack-Raghunathpur-Rahama-Paradeep: Doubling of Nergundi-Cuttack-Raghunathpur is basically done. There is a budget of 0.1 crores for this in 2011-12 and so far 178.19 crores have been spent on this out of a total estimated budget of 180.24 crores. Doubling of Rahama-Paradeep is also basically done. There is a budget of 0.1 crores for this in 2011-12 and so far 78.72 crores have been spent on this out of a total estimated budget of 80.76 crores. There is no mention of the Raghunathpur-Rahama segment in the budget, but the maps show that this part is doubled. In other words doubling of this whole segment is done.
- Cuttack-Barang: This year there is an allocation of 39 crores for this. With this allocation, by March 2012, 180.2 crores is expected to be spent. This is out of a total estimated budget of 186 crores. In other words by 2012 March this will be almost done.
- Barang-Khurda Rd 3rd line: This year there is an allocation of 39 crores for this. With this allocation, by March 2012, 220 crores is expected to be spent. This is out of a total estimated budget of 221 crores. In other words by 2012 March this will be basically done.
- Khurda Rd – Delang: This year there is an allocation of 0.25 crores. It needs another 0.96 crores to complete the total estimated budget of 69.67 crores. So this is done.
- Delang-Puri (28.7 km): This doubling was approved in 2010-11 with a total budget of 133.71 crores and an annual allocation of 2 crores. This year it has been given a budget of 35 crores. It needs another 96.71 crores before it is completed. That would mean that it will be done around in 2-3 more years. Odisha government may use the upcoming Nabakalebar in 2015 to get this done and operational before that.
- Vizianagaram-Lanjigarh Rd-Titlagarh-Raipur: The maps show that Vizianagaram-Lanjigarh Rd is double line. For the Lanjigarh-Rd – Titlagarh segment, there is an allocation of 5 crores, and there is a need of another 0.8 crores tp take it to the total estimated budget of 171.4 crores. So basically the Lanjigarh-Rd – Titlagarh segment will be done by 2012 March. The 203 km Titlagarh -Raipur segment is just getting a start. The 2011-12 budget has a 60 crores allocation for this. But it needs another 629.16 crores for completion. The total estimated budget for this segment is 691.67 crores.
- Jharsuguda-Rengali-Sambalpur: There is an allocation of 33.5 crores in this year’s budget for the Jharsuguda-Rengali segment. After that there is only a need of 7.48 crores to take it to the total estimate of 119.54 crores. So this segment will be almost done by March 2012. There is an allocation of 20 crores in this year’s budget for the Rengali-Sambalpur segment. After that there is only a need of 0.6 crores to take it to the total estimate of 113.55 crores. So this segment will be basically done by March 2012. Together they will be almost done by March 2012.
- Sambalpur-Titlagarh: This is in the initial phase. There is an allocation of 60 crores in the 2011-12 budget. By March 2011 only 39.73 crores would be spend on this. The total estimate of 950.84 crores.
- Rajathgarh-Talcher-Sambalpur: Maps show that the Rajathgarh-Talcher segment is double line. Doubling of Talcher-Sambalpur was approved in 2010-11 with an initial allocation of 2 crores. This year there is an allocation of 66 crores. The total budget is 613.27 crores.
- Bimlagarh-Champajharan-Dumetra (SER): There is a budget of 35 crores for Bimlagarh-Dumetra and another 35 crores for Champajharan-Bimlagarh. Based on the two entries in the budget, it seems the Champajharan-Dumetra part will be done by March 2012 and another 115.9 crores is need to complete the Bimlagarh-Champajharan part.
- Jakhapura-Daitari-Tomka-Jaruli-Bansapani (ECOR/SER): Bansapani-Jaruli is listed in the SER budget and has an allocation of 35 crores for this year. It needs another 8.18 crores to reach the estimated total of 90.89 crores. ECOR budget lists the segment Bansapani-Tomka-Daitari-Jakhapura. It was initiated in 2010-11 with a budget of 150 crores of which only 29.57 seems to have been spent. Its budget for 2011-12 is 70 crores. It needs another 843.38 crores to reach its estimated total of 942.95 crores.
- Bansapani-Padapahar Jn-Bara Jamda Jn-Barbil; Raj kharswan-Padapahar Jn: Maps show that Rajkharswan-Padapahar Jn – Barajamda Jn is double line. The 2011-12 budget has 5 crores each for the two segments of Bansapani – Padapahar and Bara Jamda – Barbil. After that Bansapani – Padapahar will reach its estimated total of 155.28 crores and Bara Jamda – Barbil would need 1.51 crores to reach its estimated total of 52.51 crores. So basically all these will be double lines by March 2012.
The total 2011-12 budget for doubling is 576.17 crores. See http://www.orissalinks.com/orissagrowth/archives/3272 for how this budget compares to past budgets. See http://www.orissalinks.com/orissagrowth/archives/3259 for an old projection to the future.