What is the public sector Mahanadi Coalfields Limited (MCL) up to?
Central public sector, Coal, MCL, Mining royalty, NALCO, NTPC, R & R, SAIL June 12th. 2007, 5:27pmLast week transportation of coal from Mahanadi Coalfields Limited came to a grinding halt and NALCO and NTPC Talcher that depend on that coal got into a critical situation. Following are excerpts from a Newkerala news report that mentions why MCL got into that situation.
Sources said the land losers of Zillinda, Kandhal and Solod affected by Ananta and Bhubaneswari mines stopped Ananata, Jagananath and Bhubaneswari open cast mines and close down the concerned project officers’ offices since yesterday demanding the promised job to the oustees by Mahanadi Coalfield Limited (MCL).
The villagers alleged that MCL authorities did not meet their commitments to provide 80 jobs to them till date forcing them to go for strike.
Similarly the land oustees of Kandhal marched to Lingaraj mine linked to NTPC-kaniha yesterday and stopped the output protesting the non-availability of employment to them as promised by Lingaraj authorities.
Coal transportation from Hngula and Balaram mines had been hit for the last four days due to the road blockade by Soloda villagers demanding jobs.
Angul Collector Girish S N said the authorities were monitoring the situation and senior officials dealing with land acquisition and rehabilitation had been rushed to troubled areas to negotiate with the agitating villagers.
Kalinga Times reported on a letter that CM Naveen Patnaik wrote to the PM on this issue. Following are some excerpts:
In a letter to Singh on Monday, the Chief Minister said that MCL should continue supplying coal to National Aluminium Company (NALCO) and National Thermal Power Corporation (NTPC) to help these industries continue uninterrupted power generation.
Blaming the MCL authorities for not extending the rehabilitation and resettlement benefits to the people affected by coal mining, Patnaik said the public sector undertaking should go as per the State’s R&R policy as the Centre was yet to adopt a new policy in this regard.
Extending R&R benefits to the families affected by the operations of MCL will go a long way in improving law and order situation in the region, Patnaik said.
In recent months there have been reports regarding how some R & R issues with respect to Hirakud dam oustees and SAIL Rourkela still remains unresolved after several decades. It seems that many public sector companies with their central government connections are arrogant and have not done R & R properly. As a result people do not trust R & R promises made by anyone (private or public companies) and as a result various projects that could help Orissa get out of the bottom, are getting inordinately delayed.