55,000 crore NTPC plans for Odisha

Angul, Dhenkanal, NTPC, Sundergarh, Thermal Comments Off on 55,000 crore NTPC plans for Odisha

Following is an excerpt from a PTI report.

the state-run power major NTPC is set to pump in over Rs 55,000 crore for additional capacity generation of 9,320mw by setting up two new plants and expanding the existing Talcher plant.

"Over Rs 55,000 crore will be invested in Orissa for new projects at Dadripali in Sundargarh district and Gajmara in the Dhenkanal-Angul belt and to expand the Talcher plant," NTPC regional executive director for East & North IB Pandey told reporters here today.

While the Dadripali plant, to be built in three phases, would have a capacity of 4,800mw with six units, the 3,200mw Gajmara plant would be set up in two stages, he said, adding land for them are likely to be available in about six months.

 

Push for micro, small and medium enterprises (MSMEs) in Odisha

Balasore, Balasore- Chandipur, Bargarh, Berhampur- Gopalpur- Chhatrapur, Bhadrakh, Business Standard, Cuttack, Dhamara- Chandbali- Bhitarakanika, Dhenkanal, Ganjam, Jajpur, Jajpur Rd- Vyasanagar- Duburi- Kalinganagar, Jharsugurha, Jharsugurha- Brajarajnagar- Belpahar, Kalahandi, Keonjhar, MSE - medium and small enterprises, MSMEs, Rayagada- Therubali, Rourkela- Kansbahal, Sambalpur, Sambaplur- Burla- Bargarh- Chipilima, Sundergarh Comments Off on Push for micro, small and medium enterprises (MSMEs) in Odisha

Following is an excerpt from a report in Business Standard by Bishnu Das.

To meet the infrastructure needs of micro, small and medium enterprises (MSMEs) on a priority basis, the Orissa government has reserved 20 per cent of the area in all industrial estates, industrial parks, industrial corridors and land banks for such units.

Further, the state-owned Industrial Infrastructure Development Corporation (Idco) will promote new exclusive zones for MSMEs in all major industrial hubs of the state.

The locations where exclusive industrial parks will be promoted include Kalinganagar, Barbil, Jharsuguda, Sambalpur, Dhenkanal, Rourkela, Baragarh, Balasore, Dhamara, Gopalpur, Chhatrapur, Raygada, Kalahandi and Choudwar.

Such exclusive zones will also come up near the Special Economic Zones (SEZs) in the state.

… The government has also decided that wherever land is provided to large and medium industries, 10 per cent of the land, subject to a maximum limit of 200 acres, will be earmarked for setting up MSMEs. This will facilitate the setting up of ancillary and downstream units, preferably in cluster mode, a source added.

… Sources said that Common Facility Centres (CFCs), to be set up by the Special Purpose Vehicle (SPV) constituted for the MSME clusters, would be entitled for allotment of land free of cost at various locations in the state.

… To provide assured sources of raw material for such units, the Orissa Small Industries Corporation (OSIC) and the National Small Industries Corporation (NSIC) will set up raw material banks.

The two organisations will act as nodal agencies for MSMEs and public sector resource companies will accord priority to OSIC and NSIC in supply of raw materials, which will be made available to MSMEs at the lowest possible rate.

News round-up: 3 more terminal markets at Cuttack, Berhampur & Rourkela; MOU with IPPs; 595 crores for water body upgrade; Mega food park at Malipada

Angul, Balangir, Balasore, Bargarh, Berhampur- Gopalpur- Chhatrapur, Bhubaneswar- Cuttack- Puri, Cuttack, Dam project, Dhenkanal, Food processing, Gajapati, Ganjam, Jajpur, Kalahandi, Kandhamala, KBK Plus district cluster, Khordha, Koraput, Loans, Malkangiri, Mayurbhanj, Nabarangpur, Nayagarha, Nuapada, Rayagada, Rourkela- Kansbahal, Sambalpur, Sambalpur-Burla-Jharsuguda, Sonepur, Sundergarh, Thermal, WATER MANAGEMENT Comments Off on News round-up: 3 more terminal markets at Cuttack, Berhampur & Rourkela; MOU with IPPs; 595 crores for water body upgrade; Mega food park at Malipada

1. Economic Times on 3 more terminal markets in Odisha:

Orissa government will provide four terminal market yards to enable the farmers to sell their produce at market prices…. One of the terminal has already been constructed at Sambalpur with an investment

of Rs 86 crore and three others are coming up at Cuttack, Berhampur and Rourkela,…

2. Business Standrad on MOU with five IPPs for 4800 MW power:

The cumulative capacity of these projects would be 4800 Mw and the total investment is envisaged to be Rs 23203.52 crore.

With this, the total power generation projected in the state would increase to 31100 Mw from 26300 Mw earlier.The Orissa government has already inked MoUs with 21 IPPs with an aggregate generation capacity of 26,300 Mw earlier.

… Five companies who signed the MoU included BGR Energy System, JR Powergen Private Ltd, Adhunik Power and Natural Resources Ltd, Maa Durga Thermal Power Company Ltd and Vijaya Ferro and Power Private Ltd.

JR Powergen Private Ltd would set up a 1980 Mw thermal power plant at Kishorenagar near Angul at an investment of Rs 7988 crore. BGR Energy Systems Ltd also plans to set up a 1320 Mw power plant at Bhapur in Nayagarh district at an investment of Rs 6287 crore.

Similarly, Adhunik Power and Natural Resources Ltd would set up a 1320 Mw power plant at Birmaharajpur in Sonepur district entailing an investment of Rs 8079.74 crore. All these proposals were cleared by the High Level Clearance Authority (HLCA) chaired by the chief minister Naveen Patnaik.

On the other hand, Maa Durga Thermal Power would set up a 60 Mw ((2x30Mw) power plant at Tangi in Cuttack district, involving an investment of Rs 296.95 crore. Besides, Vijaya Ferro and Power Private Ltd, planning to set up a 120 Mw power plant (IPP) at an investment of Rs 550 crore at Kesinga (Turla Khamar) in Kalahandi district.

The total land requirement for these projects have been assessed at 4360 acres and about 22,325 direct and indirect employment opportunities are expected to be created when these projects would be fully commissioned. Three projects namely BGR Energy System, JR Powergen Private Ltd, Adhunik Power and Natural Resources Ltd would source water from the Mahanadi river system, Maa Durga Thermal Power would draw water from Birupa river.Vijaya Ferro and Power plans to source water from Tel river.

3. Hindu on preliminary bids for UMPP at Bedabahal:

the government was likely to invite preliminary bids for the 4,000-MW Ultra Mega Power Project (UMPP) at Bedabahal in Orissa by April 30.

The request for qualification (RSQ) for the project may be issued by April 30.

This Bedabahal project would be the sixth UMPP project. The government has already awarded four UMPPs, of which three — Sasan in Madhya Pradesh, Krishnapatnam in Andhra Pradesh and Tilaiya in Jharkhand — have been bagged by Reliance Power.

4. Sify on 595 crores for waterbody upgrade:

As many as 1817 water bodies, mostly the minor irrigation projects (MIPs) in 20 districts of Orissa, would be revitalized under the Centrally sponsored scheme of Repair, Renovation and Restoration (RRR) of Water Bodies.

These water bodies would be revitalized within a period of three years at an estimated cost of Rs 595.14 crore.

The funding for these projects would be shared between the Government of India and the Orissa government in the ratio of 90:10 for the Maoist infested, drought prone and backward districts of Kalahandi, Bolangir and Koraput (KBK).

For the other districts, the share between the Centre and the state government will be 25 per cent and 75 per cent respectively.

While the design ayacut of all 1817 projects was 2, 48,545.86 hectares, the irrigation potential of an additional 89,110.02 hectares of land would be revived through these projects, sources said.

Most of these projects under the RRR scheme are being taken up in south Orissa’s Ganjam district. About 800 projects under the scheme are to be taken up in the district at a cost of Rs 250.87 crore.

… Apart from Ganjam and KBK, the other districts where the scheme will be implemented are Bargarh, Bolangir, Gajapati, Jajpur, Kalahandi, Kandhamal, Koraput, Mayurbhanaj, Nabarangapur, Nayagarh, Nuapada, Rayagada, Sambalpur, Sundargarh, Balasore, Malkanagiri, Subarnapur, Deogarh and Dhenkanal.

The pilot project for this scheme was implemented for 137 projects in Ganjam and Gajapati districts at a cost of Rs 18.84 crore during 2005-06 to 2008-09.

5. Hindu on Japan giving 150 crores for an irrigation project:

Japan will also give … over Rs 150 crore for Rengali irrigation project in Orissa.

6. Hospitalitbizindia on a mega food park at Malipada, Khurda:

Government of India is likely to set up a mega food park and a marine food park at Malipara near Khurda in Orissa with an area of 282 acres. This information was given by Subodh Kant Sahai, Union Minister for Food Processing while responding to a demand raised by Naveen Patnaik, Chief Minister, Orissa at the Orissa Investors meet 2010.

Odisha HLC clears project worth 48,500 crores on Jan 27th 2010

Angul, Dhenkanal, High Level Committee, Nayagarha, Sonepur, Sundergarh, Thermal Comments Off on Odisha HLC clears project worth 48,500 crores on Jan 27th 2010

Following is an excerpt from a report in Business Standard by Nageshwar Patnaik.

… All these projects will create employment opportunity for nearly six thousand people

The investment proposal includes setting up of five new thermal power projects and expansion of two existing power plants.

.. The new power projects cleared by the committee include 3200 MW plant National Thermal Power Corporation (NTPC) at Dharanipali in Sundergarh district (Rs 18,000 crore), 2000 MW plant by Orissa Power Transmission Corporation Limited (OPTCL) at Rengali (Rs 8,250 crore), 1320 MW plant by BGR at Bhapur in Nayagarh district (Rs 6,300 crore), 1980 MW plant by JR Power Gen Private Limited at Bainda in Angul district (Rs 8,000 crore) and 1320 MW plant by Adhunik Power Company Limited at Birmaharjpur in Sonepur district (Rs 8000 crore)

The existing projects which were given permission to go for expansion are Chambal Infrastructure Limited (from 1200 MW to 1320 MW and GMR Limited (1050 MW to 1400 MW).

Chambal Infrastructure Limited – which has its plants at Siria in Dhenkanal district will invest Rs 5000 crore while GMR Limited will put in Rs 6000 crore at its Kamalanga plant in the same district.

Solar and Biomass power units in Odisha

Balangir, Bio-mass, Cuttack, Dhenkanal, Ganjam, Hydro, Solar and other renewable, Kalahandi, Kandhamala, Khordha, Nabarangpur, Nayagarha, Puri, Rayagada, Sundergarh 1 Comment »

Bishnu Das’s article in Business Standard lists many of the solar and biomass power unit projects that are in the pipeline in Odisha. Following are some excerpts.

Solar power units:

  • 5 Mw power plant of RSB Energy Pvt Ltd in Sundergarh district
  • Enzen Global Solutions’s 5 Mw solar power plant in Khurda district
  • Lanco Solar’s 5 Mw solar plant in Cuttack district
  • Sunark Solar’s 5 Mw power plant in Puri district
  • Kolkata based SREI Infrastructure’s 5 Mw solar power plant in Bolangir district
  • Moserbaer Pvt Ltd’s 5 Mw grid interactive solar photo voltaic project
  • Sahara India’s 5 Mw solar power plant

Biomass power units:

  • Rice husk based power plant being set up by Shali Vahana Green Energy Ltd at Nimidha village in Dhenkanal district
  • Satya Bio-Power Industry Ltd planning to set up a 10 Mw plant in Ganjam
  • A V N Power Projects setting up a 10 Mw power plant in Kalahandi district
  • Prasad Bio-Energy planning a 10 Mw unit in Raygada
  • Jay Laxmi Bio-Energy Ltd intends to set up a 10 Mw unit in Nayagarh
  • Another plant of similar capacity is proposed by Andhavarapu Bio-Energy in Nawarangpur

Modern bus terminal in Angul in 2 years; also in Bhubaneswar, Cuttack, Sambalpur and Dhenkanal

Angul, Anugul- Talcher - Saranga- Nalconagar, Bhubaneswar- Cuttack- Puri, Cuttack, Dhenkanal, Khordha, Modern Bus Stands, Sambalpur, Sambaplur- Burla- Bargarh- Chipilima Comments Off on Modern bus terminal in Angul in 2 years; also in Bhubaneswar, Cuttack, Sambalpur and Dhenkanal

Following is from Samaja.

Following ad is from Orissa Business Blog.

Single Window Clearance Committee of Orissa approves several projects worth 30,000 crores

Air separation, Aluminium, Ancilaries, Auto, Bhadrakh, Cement, Cold rolling mills, Cuttack, Dhenkanal, Ferro-chrome, Jajpur, Jajpur Rd- Vyasanagar- Duburi- Kalinganagar, Jharsugurha, Jindal, Kalahandi, Keonjhar, Ore pelletisation, Single Window Clearance (SLSWCA), Sonepur, Steel, Steel ancilaries, Sundergarh, Tathya.in, Thermal Comments Off on Single Window Clearance Committee of Orissa approves several projects worth 30,000 crores

Update: Following are some additional details from a report in Pioneer.

  • Amtech Auto Engineering would set up the complex at an investment of Rs 15,820 crore near Tangi- Choudwar. It would set up a two million tonne steel plant and 500 MW captive power plant in the complex. With this about 33,000 people will get both direct and indirect employment.

    It may be mentioned here that Jamsedpur-based RSB Trasmissions (I) Ltd, one of India’s leading auto components manufacturers, is coming up with an auto complex at Mania in Cuttack. RSB Transmission will invest Rs 430 crore in the project.

  • The committee also approved JK Cement‘s one million tonne capacity plant on the road between Athagrah and Choudwar.
  • BOC would set up an air separation plant at an investment of Rs 434 crore in Rourkela. It would produce oxygen, nitrogen and argons.
  • Bijaya Ferro Power Private Limited would set up a power plant at Keshinga in Kalahandi with an investment of Rs 550 crore. It would take water from Tel river to produce 120 MW power.
  • Ind-Bharat’s proposal to enhance its power production capacity has also got the nod of the committee. It would set up its plant at Jharsuguda with an investment of Rs 3,300 crore.
  • Facor would set up its captive power plant at Rahandia near Bhadrak.
  • Due to shortage of water, few plants have also changed their sites. Odisha Cement Power Plant (OCL) has shifted its plant site from Mania to Rajgangpur.
  • Jinadal Stainless Steel would set up its plant in Luni instead of Gajatara in Dhenkanal.
  • Kalinga Energy Power Limited would set up its plant at Jharsuguda instead of Sambalpur.
  • Scwal Brewage would set up its plant at Baranga instead of Choudwar at a cost of Rs 193 crore.
  • The Rs 1,320 crore Sahara Power project has shifted its plant to Ghantabahal from Turul.
  • German-based Gaunteman Pipery would set up its plant beneficiation plant and pelatisation plant. The beneficiation plant would come up at Barbil and the pelatisation plant at Dhamra. Around 1,605 crore would be invested in the project.
  • Aditya Alumina’s proposal to enhance its production from one million tonne to 1.5 million tonne. It would also enhance its power plant from 650 MW to 900 MW.

Following is an excerpt from Orissadiary.

The projects of Adhunic Metalics and Jindal Stainless Steel at Sundargarh and Kalinganagar, respectively have been approved. The SWCLC has also given its green signal for an air-separation plant. Projects, involving Vijay Ferrochorme and Power Pvt Ltd and Adhunic Power plant have been cleared.

Amtech Metals would establish the integrated auto-complex, first of its kind in the state. Moreover, an auto-park, steel and power plant would also be established in the complex. The cost of the entire project has been pegged at Rs 15,820 crore. All the projects are expected to provide direct and indirect employment opportunities to nearly 47,000 and 1.5 lakh people, respectively apart from bolstering the socio-economic conditions in those regions where the proposed projects would come up, state Industries Secretary, Sourabh Garg said.

Tathya has some details on the Adhunik group’s project. Following are some excerpts:

Adhunik Power & Natural Resources Limited (APNRL) has proposed to invest Rs.3883.40 crore for the 4×250 MW power plant in Birmaharajpur in Sonepur district.

… Adhunik Metaliks Limited (AML), another member of the Group has proposed to set up Down Stream Park for stainless and special products with an investment of Rs.286 crore.  … downstream industries in hot-rolling, cold-rolling utensils, kitchen and hardware.  AML has also proposed for stainless steel pipes and alloys, which received the nod.
The park will be set up at Kumarmunda in a 300 acre area in Sundargarh district.

AML is setting up steel plant at Kumarmunda with a capacity of 0.41 million ton per annum (MTPA).

Tathya has also some details on the JSL project. Following are some excerpts.

JSL Limited posed a proposal to set up a Super Critical Thermal Power Station of 1320 (660X2) megawatt capacity, which has been cleared in the meeting. The Rs.4090 crore Greenfield project will be set up at Luni in Dhenkanal district.

Most importantly JSL, which is setting up a 3.20 million ton per annum (MTPA) capacity stainless steel plant at Kalinga Nagar has proposed to set up Stainless Steel Park (SEZ) with an investment of Rs.740 crore.  … The park will promote auto components, kitchen & life style, light engineering, white goods, cold rolling, pipes and tubes, and service centre. 300 acres of land for the park is needed for the park, which will have man power requirement of more than 2000, said sources. JSL plant is likely to produce stainless steel by end of 2010 and the park is also to be completed by the same time reveal the SLSWCA Report.

The above two downstream park proposals are most likely due to the recent government focus on those aspects, before giving mining leases. The govt. needs to make sure that the down stream parks indeed materialize as proposed.

Investment proposals in Orissa that are waiting for final approval

Aluminium, Angul, Anil Agarwal, Anugul- Talcher - Saranga- Nalconagar, Bauxite, Birlas, Business Standard, Coal, Dhenkanal, Iron Ore, Kalahandi, Keonjhar, Koraput, Nayagarha, Rayagada, Sambalpur, Sambaplur- Burla- Bargarh- Chipilima, Sponge Iron, Sundergarh, Tatas, Thermal, Vedanta Comments Off on Investment proposals in Orissa that are waiting for final approval

Following is an excerpt from a report in Business Standard.

… Projects awaiting the chief minister’s nod include those proposed by National Thermal Power Corporation (Rs18,000 crore), L&T-Dubal (Rs 19,668 crore) and Lanco Babanh Power (Rs 11,402 crore) among others.

… The SLSWCA in its meeting held in March 2007 cleared the Rs 4232.54 crore investment proposal of Ashapura Minechem Ltd for setting up of a 0.5 million tonne per annum (mtpa) alumina refinery and 0.15 mtpa smelter with 300 Mw captive power plant (CPP) in Koraput district.

Similarly, NTPC proposal to set up a 3200 Mw thermal power project at Darlipali in Sundergarh district was approved by the SLSWCA in February 2008.

The fate of L&T’s proposal to set up an alumina-aluminium complex at Kusumsila near Rayagada and Vadrapali near Sambalpur in joint venture with Dubal is still uncertain.

Sources said, the HLCA is yet to consider the Rs 8,250 crore investment proposal of Orissa Thermal Power Corporation Ltd (OTPCL) to set up a 2000 Mw coal based power plant at Rengali. It is also yet to take up the Lanco Babandh Power’s application to enhance the MoU capacity from 1320Mw to 2640 Mw at Kurunti and Kharagprasad in Dhenkanal district.

The Rs 3101.86 crore proposal of Tata Sponge Iron to set up a 1.5 mtpa steel making capacity at Beliapada near Joda, recommended by the SLSWCA in May this year, is also pending for approval by the chief ministers.

… Though VAL had proposed to expand the capacity of its existing refinery at Lanjigarh from 1 mtpa to 6 mtpa, smelter plant capacity from 0.25 mtpa to 1.6 mtpa and the captive power plant (CPP) capacity from 674 Mw to 1350 Mw with a combined investment of Rs 37,440 crore, it was cleared in part by the SLSWCA.

The SLSWCA meeting held in May this year had recommended for a smelter capacity of 0.5 mtpa as the company had already achieved this level while approving the capacity expansion of the CPP to 1350 Mw without any increase in the refinery capacity.

Similarly, Hindalco Industries Ltd (Aditya Aluminium) had proposed to expand its alumina refinery capacity to 1.5 mtpa from 1 mtpa and expansion of its smelting capacity to 0.72 mtpa from 0.26 mtpa along with an increase in the CPP capacity to 1650 Mw from 650 Mw.

SLSWCA has only recommended a marginal increase in the smelting capacity from 0.26 mtpa to 0.36 mtpa and CPP capacity from 650 Mw to 950 Mw to the HLCA. Partial approval of these proposals was officially attributed to the non-availability of bauxite linkage and pending the final report of the environmental carrying capacity study taken up by the Orissa State Pollution Control Board.

That apart, the SLSWCA in its meeting on 26 August 2009 also recommended two projects of Rs 14,275 crore to HLCA. The Rs 7988 crore proposal of JR Powergen Private Ltd to set up a 1980 Mw power plant at Kishorenagar near Angul and BRG Energy Systems’s proposal to set up a 1320 Mw power plant at an investment of Rs 6287 crore at Bhapur in Nayagarh district are yet to be approved by HLCA.

Sampalpur-Angul-Howrah Special: Should it be made a regular train?

Angul, Anugul- Talcher - Saranga- Nalconagar, Balasore- Chandipur, Bhadrakh-Sarla Rd...Vizag, Cuttack, Dhenkanal, Jajpur Rd- Vyasanagar- Duburi- Kalinganagar, KGP...Lakshannath Rd - Bhadrakh, Rajathagara - Nergundi, Sambalpur, Sambalpur - Talcher, Sambaplur- Burla- Bargarh- Chipilima 18 Comments »

Update: Biswarup Basu in an IRFCA posting pointed out that based on the current schedule this train is  competitive with the 8005/06 Koraput-Howrah Express; 1 hr 5 minutes faster towards Howrah and 15 minutes slower in the other direction.  So many may not mind traveling end-to-end on this train. He thinks there is enough traffic to introduce a daily train in this route.


East Coast Railway is running eight pairs of a special train between Sambalpur and Howrah via Angul. Following is its schedule.

From end-to-end connectivity point of view the path taken by this train is longer than the regular Sambalpur-Rourkela-HWH path.

  • SBP – Howrah : 563 kms
  • SBP – Kapilas Rd (273-15 = 258) + Kapilas Rd – HWH 396  = 654 kms

However, this train would give a direct connection between Howrah and places like Angul, Talcher and Dhenkanal. A train in this route with different times and more stops could also provide direct and useful connection between Sambalpur/Redhakhol/Angul/Talcher/Dhenkanal and Jajpur Rd/Bhadrakh/Balasore.  Perhaps ECOR is exploring a regular train in this route. 

SER to start Rourkela – Bhubaneswar Express soon; its expected impact

Angul, Anugul- Talcher - Saranga- Nalconagar, Bhubaneswar- Cuttack- Puri, CKP ... Bhalulata - Rourkela - Jharsuguda Jn - Daghora , Cuttack, Dhenkanal, Jharsugurha, Jharsugurha- Brajarajnagar- Belpahar, Khordha, Railway Budget 2009, Rourkela- Kansbahal, Sambalpur, Sambalpur - Talcher, Sambaplur- Burla- Bargarh- Chipilima, Sundergarh, Talcher - Barang 9 Comments »

Update: Aug 18, 2009 – As Dilip comments below the train should start its maiden run any day now.


Dilip Mohanty writes the following in an IRFCA posting:

The much awaited Rourkela-Bhubaneswar Express (declared in the current budget in an addition to the 57 new trains) remains a mystery. A leading local daily named "SAMBAD" has reoprted that the train will start within a few weeks and the Railways Authorities at Rourkela have already received an additional time table for this train. It reports that the train will depart Rourkela at morning 05:15 hours and reach Bhubaneswar at 13:15 hours in the afternoon. After a stay of about 30 minutes at Bhubaneswar, it will depart at 13:45 hours and reach Rourkela at 21:45 hours(an expected Superfast). This train is supposed to be operated by South Eastern Railway.

This train will bring up some new convenient 1-change connections.

  • From Bhubaneswar (BBS) to Mumbai: Using this train one can go to Jharsuguda (JSG) and then take Gitanjali that leaves JSG at 21:43. 2860 Gitanjali Express reaches Mumbai CSTM at 21:30 the next day. The total time from BBS to CSTM would be 31 hrs 45 minutes, much less than 1020 Konark which takes 36 hrs 40 mins. The weeklies 2146 and 2880 take 32hrs 15mins and 30hrs 15mins respectively.
  • From Mumbai to Bhubaneswar: 2859 Gitanjali leaves CSTM at 6:00 and reaches JSG the next day at 04:25. One can then take the above Rourkela – Bhubaneswar Express to reach Bhubaneswar at 13:15. The total time from CSTM to BBS would be 31hrs and 15 mins.
  • From Rourkela to Secunderabad: Using this train one can go from Rourkela to Bhubaneswar and then take Konark to go to Secunderabad. Konark leaves Bhubaneswar at 15:15 and reaches Secunderabad the next day at 11:35. The total time from Rourkela to Secunderabad would be 30hrs 20 mins. (One can take Falaknuma that leaves BBSR at 14:05 instead of Konark; but the connection time would be much less making it risky.)
  • From Secunderabad to Rourkela: 2704 Falaknuma leaves Secunderabad at 16:00 and reaches BBS the next day at 10:40. One can then take the BBS-ROU Express to Rourkela to reach ROU at 21:45. The total duartion will be 29 hrs and 45 mins.

8 Bio mass power projects approved by Orissa government

Dhenkanal, Ganjam, Khordha, Nabarangpur, Nayagarha, Power Generation, Puri, Rayagada 2 Comments »

Following is an excerpt from a report in Steelguru.

… Orissa Government, in its bid to encourage power generation from waste has given its accord to 8 bio mass based power projects with a combined generation capacity of 90 MW by private developers.

The proposed projects are likely to be set up in Raygada, Nawarangpur, Ganjam, Nayagarh, Khurda, Dhenkanal and Puri districts. The cost per MW of power is expected to be between INR 4.5 crore to INR 5 crore depending on the location and evacuation facilities.

Moreover, the Sali Vahana Green Energy is planning to set up a 20 MW bio mass based power plant in Dhenkanal and Satya bio power Industry, a 10 MW plant in Ganjam. Prasad bio energy plans to set up a 10 MW unit in Raygada. While Jaylaxmi bio energy Limited to set up a 10 MW unit in Nayagarh another plant of similar capacity by Andhavarapu bio energy is likely to come up in Nawarangpur. Sampath Power Projects and Falcon Green Energy propose 10 MW capacity units each in Khurda and Puri respectively.

Orissa has 98% of India’s chromite deposit; only 3.27% explored

Chromite, Dhenkanal, Jajpur, Jajpur Rd- Vyasanagar- Duburi- Kalinganagar 2 Comments »

Following is excerpted from a report in Business Standard.

Though Orissa has 183 million tonnes of chrome ore, constituting 98 per cent of the total chrome deposits in the country, only 3.27 per cent of this, which comes to about 6 million tonne, has been fully explored till date.

To expedite the exploration and exploitation of chrome reserves in the state, the government has granted mining leases to 15 companies including Ferro Alloys Corporation (Facor) and Balasore Alloys.

Of the total chrome reserves in Orissa, Sukinda area in Jajpur district has the lion’s share of 173 million tonne (mt). This includes low grade chrome.

The places in Sukinda where the chrome deposits are found are Kamarda (2 mt), Saruabili (9 mt), Sukrangi (7.5 mt), Kaliapani (25 mt), Bhimatanger (98 mt), Kalarangi (0.5 mt) and Chingudipal and Tailangi (13 mt).

Out of the total deposits found in Sukinda area, 18 million tonne are of inferior quality, says the state steel and mines minister, Raghunath Mohanty said.

The Kamakshyanagar in Dhenkanal district, which adjoins Sukinda valley, has about 4.42 million tonne reserve of chromite in locations like Sandhasar, Tulasiposhi, Haladigunda and Kathapal. The estimated reserves at Kathapal are 2 million tonne.

Mohanty said, the total chromite reserve of the state is estimated at 183 million tonne, out of which 177.42 million tonne occur in Sukinda and Kamakshyanagar area.

State Level Single Window Clearance Authority (SLSWCA) clears many projects

Aluminium, Bhubaneswar- Cuttack- Puri, Business Standard, Cement, Cuttack, Dhenkanal, Jajpur Rd- Vyasanagar- Duburi- Kalinganagar, Jindal, Kalahandi, Keonjhar, Malkangiri, Ore pelletisation, Single Window Clearance (SLSWCA), State Public Sectors, Tatas, Thermal Comments Off on State Level Single Window Clearance Authority (SLSWCA) clears many projects

Following is an excerpt from a report in Business Standard.

The State Level Single Window Clearance Authority (SLSWCA) headed by the chief secretary Ajit Kumar Tripathy today cleared five projects worth Rs 2807.7 crore.

…out of the 12 proposals considered by SLSWCA, the proposal of Bhubneswar Power Private Ltd for setting up of a 2X67.5 Mw CPP was deferred. The energy department has been asked to consider the proposal from the policy point of view.

Two major investment proposals by Vedanta Aluminium Ltd (VAL) and Hindalco Industries were partially approved in today’s meeting due to non-availability of bauxite and pending the environmental carrying capacity study by the Orissa State Pollution Control Board.

VAL had proposed to expand the capacity of its refinery at Lanjigarh from one million tonne per annum (MTPA) to 6 MTPA and the smelter plant capacity from 0.25 MTPA to 1.6 MTPA. Besides, the capacity of the CPP was proposed to be raised from 674 Mw to 1350 Mw with a combined investment of Rs 37,440 crore.

The company had signed MoU with the Orissa government for the present capacity at an investment of Rs 12,400 crore. However, SLSWCA only recommended for a smelter capacity of 0.5 MTPA as the company had already achieved this level. It also approved the capacity expansion of the CPP to 1350 Mw as sought by the company. The additional smelting capacity will be considered only after ascertaining the availability of bauxite and receipt of the OSPCB study on environment. Similarly, Hindalco Industries Ltd (Aditya Aluminium) had proposed to expand its alumina refinery capacity to 1.5 MTPA from 1 MTPA at present.

Along with this, the company also sought expansion of its smelting capacity to 0.72 MTPA from 0.26 MTPA and increase in the CPP capacity to 1650Mw from 650 Mw.

SLSWCA has decided to recommend a marginal increase in the smelting capacity from 0.26 MTPA to 0.36 MTPA and CPP capacity from 650 Mw to 950 Mw to the HLCA.

It also put conditional approval to the proposal of the Tata Sponge Iron Ltd. to set up a 1.5 MTPA steel making capacity along with a 52 Mw CPP at an investment of Rs 3101 crore. While the existing sponge capacity of the company is 0.39 MTPA, it had sought to expand its capacity by 0.45 MTPA to 0.84 MTPA.

Similarly, the company proposed to set up one MTPA blast furnace and 1.6 MTPA pellet plant in a separate location in Keonjhar district. It will have to increase the steel making capacity first and after that the increase in the sponge making capacity will be allowed.

The other projects which were approved include 4 MTPA iron ore beneficiation plant at an investment of Rs 360.85 crore to be set up by Kolkata based Rashmi Metaliks at Nayagarh in Keonjhar district.

Similarly, the Rs 624.7 crore investment proposal of Rungta mines, Shyam Steel Industries proposal for setting up 2 MTPA iron ore pelletisation plant were cleared by the SLSWCA. Besides, the Toshali Cement’s proposal to expand its capacity to 2100 tonne per day from 600 tonne per day along with 3.96 lakh tonne per annum grinding unit at Choudwar was also approved.

The proposal of Orissa Thermal Power Corporation, a joint venture between Orissa Hydro Power Corporation (OHPC) and Orissa Mining Corporation (OMC) to set up 2000 MW power plant at Rengali at an investment of Rs 8250 crore also received the nod of the committee.

Jindal India Thermal Power’s proposal to increase the capacity from 1200 Mw to 1800 mw and Lanco Bhawan Power’s proposal to increase its capacity to 2640 Mw from 1230 Mw were approved for recommendation to the HLCA on the basis of strong recommendation of the energy department.

In another significant decision, SLSWCA decided not to allow any more cement plant in the state except Malkangiri district as the state does not have sufficient amount of limestone.

Ten different power plants are being established in Dhenkanal district: Samaja worries about the impact on the environment

Dhenkanal, Samaja (in Odia), Thermal Comments Off on Ten different power plants are being established in Dhenkanal district: Samaja worries about the impact on the environment

More MOUs signed in the power sector

Angul, Balangir, Bhadrakh, Cuttack, Dhenkanal, Jharsugurha, Puri, Thermal Comments Off on More MOUs signed in the power sector

Following is an excerpt from a report in Telegraph.

Eight power companies today promised to invest Rs 42,000 crore in the state to build plants that will generate over 4,780MW.

…Naveen added that his government’s initiatives during the past four years in encouraging value-added steel, aluminium and cement projects had led to promised investment of around Rs 6 lakh crore out of which Rs 50,848 crore had already been realised.

The companies, which signed MoUs today, were Astaranga Power Company Ltd (2,640MW), Sahara India Power Corporation (1,320MW), Ind-Barat Energy Utkal Limited (700MW), Jindal Steel and Power Ltd (1,320MW), Visaka Thermal Power Pvt Ltd (1,100MW), Kalinga Energy & Power Limited (1,000MW), Arati Steel (500MW) and Chambal Infrastructures and Ventures Ltd (1,200MW).

While Astaranga Power Company intended to establish 2,640MW thermal power plants in two phases at Astaranga in Puri district with an investment of Rs 11,200 crore, Sahara India Power Corporation proposed to set up 1,320MW thermal power plant at Turla village in Bolangir district at an estimated cost of Rs 5,604 crore.

Similarly, Ind-Barat Energy Utkal planned to set up 700MW thermal power plant at Sahajbahal near Banharpali in Jharsuguda district with an investment of Rs 3,150 crore. Visaka Thermal Power will set up a 1,100MW coal-based power plant at Bhandaripokhari or Banto block in Bhadrak district at an investment of Rs 4,800 crore. Jindal Steel and Power proposes to set up a 1,320MW thermal power plant at Athamallik tehsil in Angul district with an investment of Rs 5,940 crore.

Besides, the Kalinga Energy plans to set up a 1,000MW thermal power project at an investment of Rs 4,261 crore at Babuchakuli.

While Arati Steel proposes to set up a 500MW thermal power plant at Ghantikhal in Cuttack district, Chambal Infrastructures and Ventures Ltd plans to set up 1,200MW power plant at Siaria in Dhenkanal district.

According to the MoUs, the state would get the benefits in shape of contribution to the environment management fund, value-added tax, coal royalty and water cess.

Around 1,174 to 1,370MW of power would be available to Orissa at variable cost (less than Rs 1.50 per unit), depending on the coal block availability.

This benefit would be extended to the consumers so that got power at cheaper rate, said energy secretary P.K. Jena, who signed the MoUs on behalf of the government.

 

Single window clearance for L&T’s power project in Dhamara and JSPL’s power project in Dhenkanal district

Bhadrakh, Business Standard, Dhamara- Chandbali- Bhitarakanika, Dhenkanal, Jindal, L & T, Single Window Clearance (SLSWCA), Thermal 1 Comment »

Following is from a report in Business Standard.

The State Level Single Window Clearance Authority (SLSWCA) headed by Orissa chief secretary Ajit Kumar Tripathy today approved 2 thermal power projects with combined investment of Rs 16,140 crore.

This includes 1680 Mw thermal power project proposed by L &T with an investment of Rs 10,200 crore near Dhamra in Bhadrakh district and 1000Mw thermal power plant proposed by Jindal Steel and Power Ltd (JSPL) at Bainda in the Dhenkanal district with an investment of Rs 5940 crore.

SLSWCA, which considered 10 proposals in the power and steel sector today approved 2 proposals, rejected two proposals while deferring its decision on the remaining 6 proposals.

The two proposals which were rejected are Surya Chakra Power Company proposing to set up a thermal power plant at Balasore and Adhunik power proposing a thermal power plant at Banto in Bhadrakh district.

Talking to the media after the meeting, A K Meena, managing director, Industrial Promotion and Investment Corporation Ltd.(Ipicol) said, due to the non availability of water in different locations some proposals have either been rejected or deferred.

He said, SLSWCA approved the proposal of the L&T Ltd. subject to the condition that the company will use sea water for its plant. Besides, it will have to withdraw the case filed against Orissa government regarding the iron ore lease. It has been suggested that the company will be allowed to sign the memorandum of understanding (MoU) with the state government only after it meets the above two conditions. Similarly, SLSWCA recommended the proposal of the JSPL for setting up a thermal power plant subject to the participation of the company in the creation of water storage capacity in river Mahanadi. The proposals which were deferred are those of Tuff Energy, Tata Sponge Iron Ltd., JR Power Gen Ltd., Poysa Power Project Ltd., Jindal India Thermal Power (capacity expansion) and Lanco group (capacity expansion).

 

Nine projects approved by the Single Window Committee

Dhenkanal, Jindal, Keonjhar, New Indian Express, Indian Express, Financial express, Ore pelletisation, Puri, Single Window Clearance (SLSWCA), Steel, Thermal, Titanium Comments Off on Nine projects approved by the Single Window Committee

Following is an excerpt from a report in expressbuzz.com.

The State-level single window clearance authority (SWCA) today gave approval to nine project proposals worth over Rs 13,000 crore.

The Ashapura Minechem Limited, the largest multi-mineral solution provider in the country and the flagship of Ashapura Group, has evinced interest to set up mineral separation plant in Puri district with an investment of Rs 910 crore. The plant will separate minerals from beach sand and it will produce titanium dioxide, widely used in paints. The project will create employment opportunities for 300 persons, Industries Secretary Ashok Dalwai told mediapersons.

The other new proposal cleared by the SWCA was a 1.2 million tonnes iron ore beneficiation and pelletisation plant by Jaiswal Nicco Industries at Harmote near Barbil in Keonjhar district. The company planned to invest Rs 452 crore and the proposed project would generate employment opportunities to 500 persons.

The proposal of Jindal Steel and Power Limited (JSPL) for capacity addition to its existing steel plant from two million tonnes to six million tonne was also approved. The steel production of the plant will be 3 million tonne through DRI (sponge iron) route and another 3 million tonnes through blast furnace route. The company has also proposed to increase the capacity of its thermal power plant from 900 mega watt to 1080 MW. The total investment of the company will increase from Rs 13,135 crore to Rs 22,440 crore.

The authority also cleared the expansion plan of International Mineral Trading Company having a pelletisation plant at Barbil in Keonjhar district. The company proposed to set up an iron ore beneficiation plant of 1.5 million tonne capacity with an investment of Rs 175 crore.

The BRG Iron and Steel Company at Khurunti in Dhenkanal district proposed to increase its steel production capacity from 0.257 MTA to 1.2 MTA with an investment of Rs 960 crore. The project has received environmental clearance.

Shree Metallics also proposed to increase its steel plant capacity from 0.25 MTA to 0.98 MTA with an investment of Rs 709 crore. The other expansion projects include Grewal Associates sponge iron plant at Barbil to 0.25 MTA steel plant and a 15 MW power plant, Dinabandhu Steel and Power for a 0.26 MTA steel plant with 25 MW power plant and Ganesh Metallics for 0.25 MTA steel plant with 16 MW captive power plant.

Orissa getting no tax from Bhushan Steel operations In Kantabania, Dhenkanal: Samaja

Bhushan Steel Ltd., Dhenkanal, Samaja (in Odia), Steel, Taxes Comments Off on Orissa getting no tax from Bhushan Steel operations In Kantabania, Dhenkanal: Samaja

There are at least two Bhushan companies. This article is about Bhushan steel Ltd.The other company is Bhushan Power and Steel.

RSB Metaltech signs MOU with Orissa

Aluminium, Bauxite, Dhenkanal, INVESTMENTS and INVESTMENT PLANS, Rayagada, Rayagada- Therubali, Statesman, Telegraph, Thermal Comments Off on RSB Metaltech signs MOU with Orissa

Following is an excerpt from a report in the Statesman.

The state government today inked an MoU with RSB Metaltech for setting up of an integrated light metal aluminum complex. The papers were signed by state industries and mines secretary Dr Ashok Dalwai and RSB Metaltech MD Mr SK Behera

In the first phase, the proposed company, with an investment of around Rs 6,800 crore, will produce about 7 lakh tonnes per of alumina. In the second phase, nearly 1.75 lakh tonnes of aluminium is expected to be produced from the plant. The produced aluminium will be used for production of finer parts in motor vehicles, aerospace, railway and construction industry.

While the mining and refinery units of the project will come up a Rayagada, the smelter unit and power plant are proposed to be set up at Kamakshyanagar in Dhenkanal.

Chief minister Mr Naveen Patnaik said that the project will generate about 11,000 direct and the equal number of indirect jobs. "This project, along with its alumina refinery at Rayagada and Gopalpur port will form an industrial corridor in southern Orissa," Mr Patnaik said adding that the corridor will help fast development, alleviation of poverty and improvement of life of the local people in that region. He suggested that provisions should be made to provide technical education to local youths. "The rehabilitation, resettlement and environment aspect should be taken proper care of," he pointed out.

The Union minister has been requited to expedite and complete the "Therubali-Gunupur railway project to enhance the connectivity in that region," he informed.

I wonder about the progress of the earlier plan of establishing an auto component manufacturing plant near Cuttack by RSB Transmission. (See  http://www.orissalinks.com/orissagrowth/archives/421.)

HLCA clears more projects

Aluminium, Bhadrakh, Business Standard, Cuttack, Dhamara- Chandbali- Bhitarakanika, Dhenkanal, High Level Committee, Hydro, Solar and other renewable, Jajpur Rd- Vyasanagar- Duburi- Kalinganagar, Jharsugurha- Brajarajnagar- Belpahar, Keonjhar, NALCO, NTPC, Ore pelletisation, Puri, Sambalpur, Sambaplur- Burla- Bargarh- Chipilima, Steel, Thermal 1 Comment »

Following is from a report in Business standard:

The Orissa government today cleared projects worth Rs 1,27, 727 crore in steel, aluminium, power, downstream and ore beneficiation sectors.

The list includes 3 projects in the steel sector, 2 projects in the aluminium sector, 6 projects in the power sector, one downstream unit, and two beneficiation and pelletisation units.

… enhancement of the steel capacity of Jindal Stainless Limited (JSL) from 1.6 million tonne per annum (mtpa) to 3.2 mtpa at Kalinganagr Industrial Complex at an investment of Rs 16,266 crore and enhancement of capacity of Visa Steel in the same location from 0.35 mtpa to 1.5 mtpa at an investment of Rs 4995 crore were approved by HLCA.

The public sector aluminum major Nalco’s proposal to set up a 0.5 mtpa alumina smelter and 1260 mw power plant in two phases (840Mw + 420 Mw) at an investment of Rs 16,345.89 crore was also approved. Though the company preferred to set up the project at Brajarajnagar, the location might change. The company is seeking 275.30 hectares of land for the smelter and 575.7 hectares for the power plant.

Similarly, the proposal of the Navayuga Steels for setting up a 12 mtpa port based steel complex at Astaranga in Puri district at an investment of Rs 34,000 crore was cleared by the HLCA. The project will come up in 4 phases and the government will not commit any raw material linkage to it.

Though the company requires 4000 acres of land, the government will assess the land requirement as per the benchmarking report after the company submits the detailed project report (DPR), the minister added.

The public sector National Thermal Power Corporation (NTPC) was given the green signal to set up a 3200 Mw coal based mega power plant at an investment of Rs19,840 crore near the village Gajamara in Dhenkanal district. It requires about 3000 acres of land for the project and will source water from Mahanadi.

However, Jindal Stainless’ proposal to set up 1000 Mw Independent Power Producer (IPP) at an investment of Rs 4090 crore in the same location did not find favour with HLCA with the committee asking the company to change the site of the project.

Other projects which received the nod of HLCA are Rs 6800 crore investment proposal of RSB Metal-tech for setting up 1.4 mtpa alumina refinery, 0.35 mtpa aluminium smelter and 900 Mw CPP at an investment of Rs 6800 crore, Kalinga Energy’s 1000Mw thermal power project at an investment of Rs 4261 crore at Babuchakuli, Arati Steel’s 500Mw thermal power project at Ghantikhal in Cuttack district, Rs 4994 crore investment proposal of Chambal Infrastructures and Ventures Limited for setting up of 1200Mw thermal power plant at Siaria in Dhenkanal district.

Besides, Hyderabad based Lanco Solar’s 250 Mw fully integrated plant to manufacture crystalline silicon solar cells at an investment of Rs 2800 crore in Dhenkanal district, Bhushan Power and Steel Limited (BPSL)’s downstream and ancillary complex in Sambalpur district at an investment of Rs 1953.87 crore, JSW Steel’s proposal to set up 7 mtpa iron ore beneficiation plant and 5 mtpa pelletisation plant at Kamalang in Sundergarh district at an investment of Rs 1450 crore were through in today’s meeting.

Besides, the proposal of Welspun Orissa Steel to set up a 4.5 mtpa beneficiation plant at Nayagarh in Keonjhar district and 4.4 mtpa pellet plant at Dhamra in Bhadrakh district with an envisaged investment of Rs 1963 crore, the proposal of Astaranga Power Company to set up a 2460 Mw power plant at Astaranga at an estimated cost of Rs 11,200 crore were approved by the HLCA.

However, the decision on the 700 mw (Rs 1007crore) power plant proposal of Ind Bharat Energy, 1320 mw (Rs 5604 crore) power plant proposal of Sahara India Power Corporation and the 1100 Mw (Rs 4810 crore ) power plant proposal of Visaka Thermal were deferred.

National waterway Bill passed in Lok Sabha and Rajya sabha

Balasore, Bhadrakh, Cuttack, Dhenkanal, Jagatsinghpur, Kendrapada, National Waterway 5 Comments Off on National waterway Bill passed in Lok Sabha and Rajya sabha

Update: It was also passed in the Rajya sabha on 24th October 2008.

Following is from the Lok sabha Synopsis of 23rd Ocvtober 2008.

NATIONAL WATERWAY (TALCHAR-DHARMA STRETCH OF RIVERS, GEONKHALI-CHARBATIA STRETCH OF EAST COAST CANAL, CHARBATIA-DHAMRA STRETCH OF MATAI RIVER AND MAHANADI DELTA RIVERS) BILL-2006
AND

NATIONAL WATERWAY (KAKINADA-PONDICHERRY STRETCH OF CANALS AND THE KALUVELLY TANK, BHADRACHALAM-RAJAHMUNDRY STRETCH OF RIVER GODAVARI AND WAZIRABAD-VAJAYAWADA STRETCH OF RIVER KRISHNA) BILL-2006

THE MINISTER OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS (SHRI T.R. BAALU) moving the motion for consideration of Bills, said:  From time immemorial, inland water transport has served as a cheap and economic means of transport in India.  With the advent of faster means of transport, i.e., rail, road and air, inland water transport has got neglected.  Inland water transport has, however, maintained its edge over the other modes of transport in certain areas where it enjoys natural advantages.  Its energy efficiency, low pollution and potential for employment generation are universally accepted.  Since independence, the Government is seized of the need for developing inland water transport infrastructure to restore its rightful place in the overall transport scenario of the country.  The subject of inland water transport finds place in all the three Lists of the 7th Schedule to the Constitution of India.  The role of the Union is, however, limited to regulating shipping and navigation on the national waterways declared, as such, by Parliament.  The responsibility and executive authority for development and maintenance of all waterways other than national waterways rest with the State Governments.  Keeping in view the slow pace of the development of inland water transport in our country, several Committees were constituted by the Government of India which have recommended declaration of certain important inland waterways as national waterways.  The Government of India has constituted Inland Waterways Authority of India for development, maintenance and regulation of national waterways for shipping and navigation.  The infrastructure facilities on the existing three national waterways are being created by it to make them fully functional.  Most of the State Government do not have resources to develop their waterways for shipping and navigation due to which most of the waterways remained totally neglected and unexploited for navigation.
 Before a waterway can be considered for being declared as a national waterway, it is essential to undertake techno-economic feasibility study including hydrographic survey and traffic studies of such waterways to assess the extent of improvement works required for their development and their financial implications.  Based on this study and the potential of improvements in inland water transportation, it is now proposed to declare some waterways mentioned in the Bills as national waterways.

 SHRI DHARMENDRA PRADHAN:  Infrastructural development is very important for economic development of our country.  Though, delayed, but then it is appreciable that a proper thinking regarding waterways in the country is taking shape.  Three waterways of Orissa have been mentioned.  I would like to mention Talwer.  It will become an important waterway. About 60 million tonne of coal is produced in this area.  Though, coal is mined, it is arduous to transport it.  It will be really a beneficial step to form a waterway for this purpose.  A water route has been formed by linking the tributaries of Mahanadi and Brahmani.  This is a matter of challenge.  We must have water in Brahmani river if at all we have to run it for the year along.  If there is a scheme through which Mahanadi water enters into Brahmani, it will keep Brahmani perennial. It shall be really very much beneficial if the Government of India, the Planning Commission and the Minister of Water Resources deliberate in this regard.


 SHRI LAKSHMAN SETH:  We have so many modes of transportation like airlines, railways and roads but waterways is also an important mode of transportation of our cargo and commodities.  This is very much neglected in our country.  Transportation through water is always cheaper, eco-friendly and environment-friendly so waterways should be developed.  Our experience is not so much satisfactory because already long before, one waterway, i.e. Allahabad and Haldia waterway, has been declared as a national waterway.  But, I think, infrastructure development has not taken place so far.  Terminal has not been done adequately and dredging has not been taken up to the considerable limit.  That is why, this important national waterway has not been used properly.

 Our nation is facing a severe crisis in fuel.  So fuel would be saved.  At the same time, environment will be certainly cleaned.  That is why there should be a law enforcing the public sector to use this mode of transportation in inland waterways so that the inland water becomes useful and at the same time the nation will also save huge money on account of fuel.

 The declaration of these two important waterways as a national waterway will help immensely irrigation and transportation of various types of cargoes and commodities.  At the same time, I am requesting the hon. Minister to declare the waterways from Haldia to Sundarban as a national waterway.  Another issue which I would like to bring to the notice of the hon. Minister is that in Bangladesh, there is an anchorage on the river Ashuganj.  If the Government of India can manage to have this anchorage then the distance between Halida, Kolkata and the North-Eastern States will be reduced remarkably and fuel will also be saved.   I congratulate the hon. Minister for bringing this Bill but at the same time I would request him to arrange adequate fund for implementation of the various infrastructural facilities.  Further, I would request you to look into the interest of the farmers.

            SHRI GANESH PRASAD SINGH:  The responsibility for the management of rivers lies with the State Governments but they do not have sufficient resources to shoulder this responsibility.  The travel by waterways is economical and time saving also.  This Bill envisages an Authority for the development of national waterways and sufficient amount of money has also been proposed to earmark for this purpose.   So this Bill is a welcome step.

 SHRI B. MAHTAB:  It is said that the total length of navigational waterways in India is about 14,500 kilometres.  Of this, 5,700 kilometres is navigable by mechanically propelled vessels.  At present, the inland traffic is estimated at about 1,000 billion tonne kilometers and the inland water transport accounts for barely 0.17 per cent.   The House should know that IWT is not only environment-friendly, it is also less capital intensive.  Lack of infrastructure, absence of fixed scheduled services, poor navigational aids, lack of connectivity, longer river distances and thin flow of private investment are the major factors that have stifled the development of this mode of transportation. Now we are considering the East Coast canal integrated with the Brahmani River along with Mahanadi Delta Rivers.  It is said that around 18.07 million tones of inland water transport traffic is expected to be carried out on the proposed waterway after it is fully development in eight years time.  I would like to suggest that the Government should prepare a roadmap for an Integrated Transport Policy for enabling better inter-connectivity amongst the multiple modes of transport.  There have to be provisions for an institutional framework for development of inland water transport sector.  There is a need to increase cost recovery and also to commercialise IWT industries.  An Action Plan should be in place to address the growing demand of repair and service facilities of IWT vessels.  I hope, the proposed national waterways will boost the rural economy and help decongestion of roads and rails.  I hope it will provide port-hinterland connectivity, especially between Talcher to Dhamra.  It will generate employment and also increase tourism activities in that region. I am sure that the Government must have appointed a consultant for undertaking techno-feasibility study and preparation of detailed project report for this waterway.  I hope that the interest of Orissa will not be compromised due to development of this proposed national waterway.  Lastly, I must say that regular dredging of riverbeds would be necessary.  The infrastructure currently available on this waterway is not adequate for safe, convenient and sustained shipping and navigation purposes. Once it is developed, there is ample scope to have substantial quantum of inland water transport traffic, but first the parameters are to be met and that too, within a specific time frame.

 SHRI M. SREENIVASULU REDDY:  I rise to support this Bill.  All of us know that there are different modes of transport.  Waterway is the cheapest, though slow.  I am happy that Buckingham Canal-which flows through Ongole, which is my Parliamentary Constituency, has been included in this Bill for the development.  There has been a lot of pressure from people living in between Buckingham Canal and Bay of Bengal for construction of bridges to enable them to cross the canal. I request that the bridges at the required spots may be constructed immediately. The area covered between Kakinada and Chnnai along with rivers Godavari and Krishna as Waterway is 970 kms.   There are 14 terminals that are being planned in this Bill.  Out of these 14 terminals, in my Parliamentary Constituency there is only one terminal, which has been stipulated in this Bill.  I will request the hon. Minister to include two more terminals namely, at Karedur or Ramayapatnam and Thummalapantawar near Kavali. There is one more important point that waterways do not provide door-to-door service independently.  Therefore, it is necessary that these are connected with rail or road modes for total transport linkages.  In my Ongole Parliamentary Constituency there is lot of potential in Granite/tobacco/Garments, food grains, firewood, etc. and providing of connected mode of transport to Buckingham Canal will help a lot.   The Inland Waterways Authority of India could make the National Waterways functional fully subject to availability of funds. Any delay will only add to the miseries in the field of transport. Hence, I again impress upon both the Central and the State Governments for an urgent action in this regard.

 DR. BABU RAO MEDIYAM:  Supporting this Bill, I wish to say that the delta region around Krishna Godavari Rivers was developed almost 160 years ago during the British times.  The present canal system is being used only for irrigation purposes.  These canals are now under the control of the Irrigation Department, and the irrigation canals are being maintained and regulated by the Water Users Associations in our State.  Now, these canals are going to be used for navigational purposes and there is a lot to be done in this case.  I would request the Minister to take necessary action in this regard, especially on the stretch between Bhadrachalam and Rajahmundry.  There is a proposal for a great barrage of Polavaram.  This has to be linked to the existing canals.  The Irrigation Department is not spending even a pie on these canals.  If these canals come under the National Waterways Authority, then what would be the allocation?  What is the role of the Water Users Associations?   Moreover, the existing terminals on the banks of the River Godavari should be taken care.  If ever this Polavaram Dam project comes up, then most of these present terminals would be submerged.  To regulate everything, you have to explore this Bhadrachalam-Rajahmundry stretch of canal.  A lot needs to be done on the legal and financial front also.  Anyhow, I strongly support this Bill and I request this to be amended.

 SHRI ALOK KUMAR MEHTA:  I support this Bill.  I want to impress upon the authorities that, in 1985, the waterway from Allahabad to Haldia had been declared as the National Waterway.  One point of this waterway falls in Patna also.  Haldia Port is very near to this point.   In the beginning, points and ports had been constructed but lot of problems have cropped up, for want of proper dredging.  This waterway needs to be cleared.
Similarly, inland waterways system can be given a nod in view of the heavy traffic density in Patna.  The UPA Government would indeed do a great job if it declares it a National Waterway and undertake its maintenance and total infrastructure cost as it is beyond the capacity of any State Government alone.  However, if they undertake dredging the menace of flood can be averted to some extent along with the development of national waterways.

SHRI S.K. KHARVENTHAN: Inland water transport is an economical, fuel-efficient and employment-oriented transport.  The present waterways in the above ways are unsuitable for shipping and navigation.  Hence it is necessary to develop the infrastructure in river and canal portions by deepening and widening the bed for safe and convenient shipping operations.  The proposed infrastructural developments are planned to be completed within few years period in a phased manner.  I request the hon. Minister to take steps for completing the work as early as possible.
With the policy of economic liberalization Government of India has allowed private sectors for port development.  Hence, I request the hon. Minister to allow private participation in shipping in these stretches.  It will increase the service as well as employment opportunities for unemployed youths.  Another important aspect is regarding oil pollution in the above stretches.  Government has to take steps to establish Pollution Prevention Equipment in all terminals to protect and safeguard the river environment.  The Ministry also must take steps to provide all necessary facilities for day and night navigation.  Furthermore, the Government of India has to provide all assistance to states to develop other waterways in various States.

Inland Water Transport is one of the oldest and cheapest modes of transport.  But unfortunately, we have failed to develop it.  If the Ministry of shipping is taking a serious view on this subject, then it should and must come forward to allow Joint Venture of Private sector participation in this field.  The Standing Committee has also recommended Joint venture participation.  The Government should also concentrate on providing proper repair and regular servicing facilities for operating vessels in these waterways.

SHRI KHARABELA SWAIN: I thank the hon. Minister for introducing such a Bill.  However, I would like to emphasis upon the hon. Minister that nowadays most parts of the East Coast Canal passing through the district of Balasore have been encroached by various people.  In some places, there is virtually no sign of any canal because of the shrimp farming.  I shall appeal to the hon. Minister that he should see to it that the land which have been encroached by the land mafia should be recovered by the State Government.  Let the State Government take very stringent action with regard to this.  Then I come to the repair of the embankment.   In most places, there is no existence of any embankment now.  Those places should be developed.  If both sides of the embankment could be developed under the Pradhan Mantri Gram Sadak Yojana, it will also provide very quick communication facilities for the people.  This will also provide an embankment for the prevention of floods.  Further, in many places, the farmers have put cross bunds.  They have raised many other obstacles.  Thus there is no drainage water facilities available.  Hence if a canal is dug, it could be drained and a proper drainage water facility could be provided there.  That would also save a lot of people and a lot of property being destroyed every year due to flood.  While dredging this canal, he should also provide for some small bridges across the canal in regular intervals because cattle will cross, because people will be going to their paddy fields for cultivation along with their cattle, bullocks and cows.  So, all these things should be provided now in a planned manner.

 The hon. Minister is also requested to go for sluice gates in order to prevent the salty water of the sea entering into the paddy fields.  I will appeal to the hon. Minister that he should set a time frame for the completion of these projects.  Otherwise, for eternity they will remain on paper and they will not be implemented at all.

 SHRI ADHIR CHOWDHURY: India has already three National Waterways and we are going to have two more National Waterways.  But we have to have some introspection whether just declaring some waterways as National Waterways will serve the desired purpose.  India is a country which has been endowed by the nature of so many rivers.  In spite of the huge potentiality that we have in our country we are able to exploit a very negligible portion of our waterways.  In our multi-mode transport system, inland water is so negligible that inland water transport system enjoys less than one per cent.  The fact is that in spite of plenty of potentiality in so far as inland water transport system is concerned, we have grievously failed to exploit the enormous potentiality and the enormous advantages in terms of fuel efficiency, in terms of eco-friendliness.
 So, first of all, what I propose to the Government is that we should offer some lucrative incentive to the private sector so that they could be drawn to the inland water transport system.  Only by the endeavour of the Government, we cannot attain our desired goal and to draw the attention of the private sector.  Our nature has itself done the engineering work for the inland water transport.  Therefore, we have the enormous leverage in this sector. The cost of development inland waterways is 5 to 10 per cent of the cost of developing an equivalent rail way or a four-lane expressway.  Insofar as maintenance cost is concerned, the maintenance cost of an inland waterway is only 20 per cent of the maintenance cost of an equivalent roadway.  However, we have failed to exploit the potentiality.

 We know that the entire State of Assam is prone to flood.  The highest river route is available in Assam so, if we are able to develop an appropriate inland waterway system in the Assam Region, I think it will be a great benefactor to the entire North-Eastern Region.  Furthermore, it will add a new dimension to our Look East Policy also.  We can cover the North-East and West Bengal by the inland water transport system and the entire route could be shortened.  It will also entail the growth of trade and commerce.  The three national waterways are there. I would like to know whether we have achieved the target, the goal before commissioning of the other three national waterways.  It will indicate whether the further declaration of national waterways will be lip service or will be a real objective of our country.
 I have a little confusion.  I would lime to know from the hon. Minister whether this amount of Rs.1,526 crore is the consolidated amount for both the national waterways or this amount pertains only to Geonkhali-Charbatia Stretch of East Coast Canal and the other amount of Rs.542 crore pertains to Kakinada-Pondicherry Stretch of Canal.  I once again appreciate our Government for bringing this Bill because when trade and commerce in our country is increasing, naturally we are facing a severe constraint in our existing modes of transport.  So, we need other avenues of transport and in this regard, inland waterways could be an ideal mode of transport in our country.

SHRI BHANU PRATAP SINGH VERMA:  Transportation of goods by roads is costly.  Whenever we have to send food articles to Kolkata, we do not get railway boggies as a result of which these articles of Bundelkhand and nearby areas do not reach Kolkata and other parts of the country.  Therefore, we want that inland waterway on the Yamuna river be restored and a port should be constructed at Kalpi Nagar so that unemployed youth of the above area could also get employment there.  Moreover, the waterways are also the cheapest means of transportation.

 SHRI SURESH PRABHAKAR PRABHU:  In fact, for a long-long time, the entire merchandise, the entire trade routes were passing through the great rivers of India.  Therefore, the waterways are not something new that we are innovating now.  Unfortunately, we neglected it and we are paying a price for it.  But I am very happy that now we are going back to the basics and we are now trying to create waterways for the country.  It will be cost-effective.  There several Ministries dealing with water.  The ministry of Shipping is now going to deal with one aspect of that.  So, when we are developing waterways.  I only hope and wish and really expect that the Ministry of Shipping will take into account the overall needs of the water sector in the country as a whole while planning this.  Floods have become common phenomena in India.  At the same time, some other parts of the country are constantly facing drought.  This is a golden opportunity; when the Minister is trying to create waterways for the country, why not also he integrates the drought and famine phenomena which happens all the time?

 SHRI GIRIDHAR GAMANG:  I support both these two bills because they would lead to economic development of the country and they would give new life to Indian inland waterways network.  There should be integration between your Department and the Department of the concerned State Government.  These two Departments will have to be integrated, not financially, but in respect of there aspects the Central Government will have to take the support of the State Government.

SHRI BIKRAM KESHARI DEO:  I completely support the Bill and welcome it because this will integrate the entire rivers with one another, and it will be direct link.  As the States do not have resources to develop inland waterways, it is high time that the Centre is now concentrating on developing these waterways.  Economically it is a very viable project.  You can use the flow of water for transportation of goods.   There has been a long standing demand in the State of Orissa that an Inland Waterways Regional Office should be opened because Mahanadi delta is a massive delta.  This will also enhance export and import activities.  Besides that, as Orissa is prone to natural disasters, this East Coast Canal, which we are developing now, will have a deterrent effect on storms and Tsunamis, and it will be a mode of transport to the entire interior Orissa.  After Independence, so many big water bodies, infrastructures and big dams have come up.  It is because of the formation of these dams and impounding of water, thousands of villages are on the other side of the reservoir thereby creating problems for the people to deliver the goods like PDS, health related activities, development activities, and transportation of people.  For example, in my constituency, Upper Indravati project is there.  It is a huge inland water reservoir covering 110 square kilometers.  It has with four dams and eight dykes.  There are about 72 villages on the other side of the reservoir.  So, to reach those 6-7 villages, we have to take a detour of nearly 100 kilometres.  But if the waterway is there, it will be about within 25 to 30 kimometres.  So, I request the hon. Minister, that the Inland Authority should be created for these big reservoirs for movement of PDS and for taking up other Government related activities.

 KUNWAR MANVENDRA SINGH (MATHURA):  I feel for the first time that after independence such a good bill has been introduced in the Parliament that is a welcome step as it would be beneficial.  Before Independence when the East India Company came to India it started inland waterway from East to West.  But gradually not much importance was given to it.  So its losses are before us today.  But today the need of the hour is that we should also gradually undertake such projects for other rivers of the country also.  Rs. 1000 crore were provided for cleansing the Yamuna river.  But we see that even after spending so much of money, sewer water and industrial waste are still being discharged into Yamuna which is really a cause of grave concern.

A project for the cleaning of the Rivers was undertaken during the regime of Late Rajiv Gandhiji, however, no special attention has been paid to this project.   River Yamuna is in a very bad condition today.  But we can develop it for waterways  which could include passenger transport as well.  If we can start waterways for passenger transport from Delhi to Agra, lakhs of tourists would travel thereby, thus developing it as a good mode of transport.  Besides, we can clean and beautify river Yamuna.  At the same time, rivers of the country need to be linked, as it would increase the flow of water in the river.  We would be able to ward off the damage caused by the floods and save crores of rupees and many lives. If we construct dams on the river, we would be able to generate hydro-power and provide irrigation facilities thereby curbing the menace of floods.  Likewise, a pollution free environment would be created and cheap mode of transport will be in place reducing the pressure on the roads.  It would help to set up new industries along the rivers in the remote areas. It would generate employment and develop the rural areas.  I would like to suggest that we need to formulate a comprehensive scheme for the rivers of the country.  Hon’ble Minister has taken a good initiative and I hope in the time to come, we will be able to develop a viable system and clean environment through our rivers in the country.

SHRI LAKSHMAN SINGH: Hon’ble Minister deserves to be congratulated for the Authority, which is sought to be set up.  However, we hope that the potential for the development through the rivers need to be properly addressed and considered.  We hope him to work with the national perspective.  We have a great potential in the North India. Likewise, there is a major river, Chambal, which flows perennially.   It has been included in the linking project too.  This river passes through three states i.e. Uttar Pradesh, Madhya Pradesh and Rajasthan.  If a waterway is developed through this river connecting these states, the problem of dacoity would be addressed to a great extent.  Besides, this mode of transport would be fairly cheaper and economical.

           SHRI T. R. BAALU replying said:  First of all, I would like to thank all the hon. Members who have deliberated in this discussion.  Definitely, all the deliberations that have been made by them are a matter of great guidance for me.  Since time immemorial, inland waterways transport has served as cheap and economic means of transport.  People are using this waterway transport as they are conscious of the issue of environment.  As you know, Allahabad-Haldia is Waterway No. 1, Sadiya-Dhubri is Waterway No. 2, and Kollam-Kottappuram is Waterway No. 3.  However, in all these three waterways, we could not achieve much success.  1985 onwards the Governments have not given the necessary attention towards this waterway system. The waterway transport has not developed to the extent other countries have developed it.  I would like to draw the attention of the august House to what we have done to develop inland waterways during the UPA period. A revised action plan for making the existing three national waterways fully operational has been drawn and it will be functional from 2010 onwards.  Funds have been provided to the extent of Rs. 961.64 crore. Investment of approximately Rs. 415 crore has been made between 2004 and 2009.  Seven terminals on National Waterway No. 3 at a cost of Rs. 10.32 crore have been constructed and commissioned. Low level jetty of a new fixed terminal capable of handling containers was constructed at Patna and high level jetty at Patna has been sanctioned.  Low level jetty at Pandu, Guwahati, on National Waterway No. 2 is nearing completion, and a high level jetty at Pandu on National Waterway No. 2 is under construction along with container handling cranes.  At various floating terminals, floating cranes and shore cranes have been provided.  Night navigation facilities have been installed in about 364 kilometres on National Waterway-1; 255 kilometres on National Waterway-2; and 100 kilometres on National Waterway-3.  Projects for providing state of the art 24-hour navigational aids on three National Waterways have been sanctioned and are under implementation.  Acquisition of six cutter section bridges, six watch boats, and six accommodation boats for carrying out dredging operations on National Waterway-1 and National Waterway-2 have been sanctioned.  Approval for setting up of six joint venture projects is on the anvil.  In response to suggestions and views expressed by the hon’ble Members, I would like to say that they would be duly considered .  In river Brahmani, accumulation of water will be ensured by constructing five barrages in that particular area. Environmental studies will be made.  Irrigation would not be affected.  We will definitely ensure that nobody staying nearby would be disturbed.  On irrigation and interests of the people living along the waterways, we will definitely consult the State Governments and do the needful.  As far as implementation plans are concerned, they have already been drawn and clearance have been obtained from the Planning Commission and the Finance Ministry.  Local irrigation interests will be taken care of.  We are giving priority to inland waterways transport.  We have already done the Techno-Economic Feasibility Study: DPRs are being prepared.  The DPRs which are under preparation would take care of terminal construction etc.  The social problems will be handled only after providing alternative arrangements. Definitely, we would come forward with an Integrated Water Transport Policy in consultation with all the Departments. After the addition of two national waterways, total length of waterways would become 4,460.   By 2020 the share of inland waterways traffic would be not less than two per cent.
 

An amount of Rs.1525 crore is identified for Talcher-Dhamra waterways and an amount of Rs.542 crore is identified for Kakinada-Pondicherry waterways.  An Hon. Member has said that we should encourage Inland Waterways Authority of India to function better by opening a regional office in Orissa.  It is proposed to open an office in Orisa; presently, it is planned at Dhamra-Charbatia.  We should see that whatever waterways that have already been declared, should be made functional; that is more important.

The Bill, as amended, was passed.

Reliance to lease OSRTC land

Angul, Anugul- Talcher - Saranga- Nalconagar, Bhubaneswar- Cuttack- Puri, Cuttack, Dhenkanal, Khordha, Modern Bus Stands, Mukesh Ambani group, New Indian Express, Indian Express, Financial express, PPP, REAL ESTATE, Sambalpur, Sambaplur- Burla- Bargarh- Chipilima 1 Comment »

Following is  from a report in New Indian Express.

The State Government will lease out unused land of Orissa State Road Transport Corporation (OSRTC) at Cuttack, Baripada and here to the Reliance Industries Limited (RIL) for commercial purpose.

The OSRTC has prime land at Master Canteen, Pala Mandap in Cuttack and Baripada town. The corporation will lease out the Master Canteen land to RIL for 33 years for Rs 20 crore. Reliance has proposed to open retail outlets and has agreed to pay a monthly rental of Rs 15 lakh.

The company has reportedly deposited Rs 6 crore with the Government for the OSRTC land at Baripada town. However, OSRTC will collect monthly rent from RIL for all the leased out plots. Rent will be revised every five years.

The proceeds from leased out land will be invested for procurement of more buses and modernisation of the Government bus stands.

In the first phase, five bus stands at Angul, Bhubaneswar, Cuttack, Dhenkanal and Sambalpur will be modernised under the public-private partnership.

While the bus stands of Bhubaneswar, Cuttack and Sambalpur will be renovated, two new bus stands will be developed at Angul and Dhenkanal.

The public utility has 230 on road buses and plans are afoot to add another 50 to its fleet. The corporation has submitted a proposal to the Government for pay revision of the employees, official sources said.

Oil rig and two cold rolling mills proposal cleared

Bhadrakh, Cold rolling mills, Dhamara- Chandbali- Bhitarakanika, Dhenkanal, High Level Committee, Offshore Oil rig Comments Off on Oil rig and two cold rolling mills proposal cleared

Following is an excerpt from a report in Pioneer.

Investment proposals worth Rs 1,825.61 crore were cleared by State-level Single Window Clearance Authority (SLSWCA) here on Saturday.

The SLSWCA meeting, chaired by Chief Secretary Ajit Kumar Tripathy, gave its nod to the Rs 900-crore investment project of Oceanic Shipyard Limited (OSL) along with two cold rolling mills with an investment of Rs 925.61 crore.

… IPICOL managing director Ashok Kumar Meena told the media that OSL, a subsidiary of Bengal Shipyard Limited (BSL), has proposed to set up an oil rig, offshore structure and a support vessels manufacturing and repairing unit at Dhamra in Bhadrak district with an investment of Rs 900 crore. BSL, a joint venture of Apeejay Shipping Limited and Bharati shipyard Limited, is setting up a shipyard at Dhamra with an investment of Rs 2,400 crore.

Meena said the company had asked for 950 acres of land at Dhamra to set up the facility in a period of 60 months in three phases from the date of allotment of land. The project would generate direct employment opportunity for 7,500 persons. As the net worth of the group is Rs 647 crore in 2006-07, there would be no problem of raising the funds for the greenfield project, added another official.

The proposal of the Bhuvee Profiles & Stainless Limited (BPSL) to set up a 0.790-mtpa hot rolled plates and coil rolling mill with an investment of Rs 492.66 crore at Kuranti in Dhenkanal district was cleared by the Authority, said Meena.

According to him, a sister concern of the BRG Group, BPSL would be the downstream project of the group. The company has asked for 90 acres of land, though the requirement for the project would be 45 to 50 acres, said an official.

Meena said the proposal of Rabirun Vinimay Private Limited (RVPL) to set up a 0.240-mtpa cold rolling mill complex at Kuranti with an investment of Rs 432.95 crore was also okayed.