Following is an excerpt from a report in Business Standard.

The first phase of the Naveen Jindal-promoted Jindal Steel and Power Ltd (JSPL)’s proposed 6 million tonne per annum (mtpa) steel project and 1000 Mw power plant at Angul in Orissa is expected to be commissioned in 2011-12.

The shifting of families to be displaced by the project was going on and simultaneously, the construction of the boundary wall had started. The detailed engineering would follow the completion of the rehabilitation and resettlement (R&R) of displaced persons and large scale construction would be taken up after that.

“We plan to start large scale construction work in January next year and the first phase commissioning is scheduled to be in 2011-12”, Rajesh Kumar Jha, executive director, JSPL told Business Standard.

He said, out of three villages to be shifted completely for the first phase construction, two villages had been rehabilitated completely. The remaining village would be rehabilitated by December this year. The company’s strategy of combining the project economy with the rehabilitated family’s economy has gone down well with the people. …

… the company had placed orders for civil and structural works worth Rs 1584.57 crore which was 60 percent of the estimated costs. Similarly, orders for plant and equipment worth Rs 4,034.34 crore had been placed which was about 35 per cent of the total estimated costs of plant and equipments.

The total cost of the project is Rs 22,420 crore with the first phase investment pegged at Rs 13,000 crore. The project has already attained financial closure and will have a 60:40 debt-equity ratio. While the debt component will be Rs 8,958 crore, the equity is Rs 13,452 crore.

…  While the company requires 5,279 acres for the steel plant, about 3000 acres have been acquired so far. The acquisition of additional 707 acres of private land is likely to be over by the end of this month.

Vedanta’s 300 crore township project near Jharsuguda to be comparable to RIL’s at Jamnagar

Aluminium, Business Standard, Industrial Township, Jharsugurha, Jharsugurha- Brajarajnagar- Belpahar, Vedanta 8 Comments »

Following is from a report in Business Standard.

In the midst of implementing a $4 billion aluminium project in Orissa, NRI Anil Agarwal-led Vedanta group, has started a Rs 300-crore township project with the support of a Chinese firm to accommodate its over a 1,000 engineers and technical workforce.

Claiming that the project would be comparable if not better than what Mukesh Ambani-led RIL developed at Jamnagar in Gujarat, group company Vedanta Aluminium is importing services of China’s leading architect firm ECADI at a time when reality majors are reeling under a slump.

"We at Vedanta feel it is our duty not only to provide a conducive working atmosphere, but also best living comforts," company’s Director and CEO M Siddiqi said, adding, the township project would be completed by end of next year.

The township project, a concept popularised by PSUs in India, is crucial for the overall aluminium unit, first stage of which has already been commissioned and the second stage is targeted for completion next year, to attract and retain talent in the backward area of Jharsuguda in Orissa.

The Vedanta project envisages providing sophisticated and urban living accommodations and amenities to over 1,400 employees, who are already stationed at Jharsuguda aluminium plant.

The metals and mining major plans to pump in a whopping $4 billion to ramp up the capacity of its aluminium smelter to 1.8 million tonne by 2010.

At present, its operational capacity is 2,50,000 tonne, which would go up to 5,00,000 tonne by March 2009.

For meeting its power requirement, the company has set up a 675 MW power plant, the capacity of which will go up to 1,215 MW post-commissioning of the smelter’s first phase expansion.