Archive for the 'Talcher – Bimlagarh (under constr.)' Category

Work starts on Paradeep-Choudwar-Rourkela Industrial Corridor

Angul, Anugul- Talcher - Saranga- Nalconagar, Bhubaneswar- Cuttack- Puri, Bhubaneswar-Dhenkanal- Anugul, CKP ... Bhalulata - Rourkela - Jharsuguda Jn - Daghora , Cuttack, Cuttack - Paradeep, Cuttack-Paradip, Dhenkanal, IDCO, Jajpur, Jharsuguda-Sambalpur- Bargarh, Jharsugurha, Jharsugurha- Brajarajnagar- Belpahar, Kendrapada, Khordha, Paradeep port, Paradip - Jatadhari - Kujanga, Rourkela- Kansbahal, Rourkela-Jharsuguda, Sambalpur, Sambalpur - Talcher, Sambalpur-Burla-Jharsuguda, Sambaplur- Burla- Bargarh- Chipilima, Sundergarh, Talcher - Barang, Talcher - Bimlagarh (under constr.) 1 Comment »

Following is an excerpt from a report in ibnlive.com.

The state government has started work on development of a railway corridor through Choudwar to Rourkela to allow ease of inward and outward transportation of goods from the industrial hubs and mining belts along the region.

Land acquisition for the project, the first of its kind initiative by a state government, has already been initiated by the Industrial Infrastructure Development Corporation (Idco). The project would go on ground after the land acquisition and is targeted to be completed by 2015, said Idco CMD Priyabrata Patnaik on Friday.

The corridor involves development of extensive rail and road connectivity, along with provisioning of water supply and other infrastructural facilities. The corridor would encompass two track railway lines and six-lane road passing through the industrial hubs and the coal mining belts. New industrial areas and downstream units would be developed along the corridor.

Common infrastructure facilities under the corridor would solve the problems of inward and outward transportation of goods and minerals. The stretch would pass through the heart of coal mining operations in the state, which harbours about 65 billion tonne of reserves. The coal reserves in the Talcher belt only is around 43 billion tonne.

The corridor would cover 17 large and mega-industries, along with 57 other units, through the stretch from Choudwar to Rourkela. Traffic projection on the route is given out as 8.7 million tonne.

The route would have 163 km of railway track length and 465 km on road. As many as 308 minor bridges and 77 major bridges would have to be constructed on it, said Patnaik.

Note 1: The 163 km of railway track probably refers to the Talcher-Bimlagarh segment.

Note 2: Although the above report only mentions the Choudwar-Rourkela part, in earlier documents there is mention of Paradeep-Choudwar-Rourkela industrial corridor. See for example this 2009 Business Standard report. Following are some excerpts from that.

The Orissa government plans to develop an industrial corridor running from Paradeep to Rourkela through industrial hubs like Choudwar, Talcher and Sambalpur.

Though the initial proposal was to have an industrial corridor originating from Choudwar to Rourkela, the proposal was modified to extend the corridor till Paradeep to allow inward and outward transport of goods through the Paradeep port, sources said.

… The proposed industrial corridor will be in line with the Delhi-Mumbai Industrial Corridor and is designed to pass through national highway no.42 and national highway no 5 (A).

Under the project, both road and rail corridor will be developed, which will be the backbone of the proposed project. The industrial estates and down stream units would be developed over 25 km area on both sides of the corridor.

IL&FS has been appointed as the consultant for the project and it has already submitted the pre-feasibility study report to the industry department on the project. However, the detail cost of the project is yet to be worked out yet, sources added.

The latest initiative of the state government follows a similar initiative to develop a common ‘rail-road-water pipeline and infrastructure corridor’ in Meramundali-Angul-Talcher-Chhendipada belt, to facilitate movement of coal in the Talcher coalfield area.

The project is estimated to cost about Rs 5000 crore including Rs 2000 crore for 2-line rail corridor and Rs 1100 crore for 4 lane road alongside it. The land width of the proposed corridor will be 300 metre which includes 60 metre for road and 20 metre for water pipeline.

The total length of the corridor is 137 kilometre which includes length of 43 number of major bridges to be constructed on this stretch. RITES Ltd has already submitted a pre-feasibility report to the state owned Industrial Infrastructure Development Corporation of Orissa Ltd. (Idco) on the project.

The project is designed to have multi-point centralised loading stations conceived along the corridor rather than individual bulb connections with a view to avoid interference or wastage of coal bearing areas. Road and water pipe alignment will run parallel to rail alignment, sources said.

It will be connected to rail line at three locations- Jharpada, Angul and Budhapanka. The common corridor will have multiple entry and exit points and no surface crossing. Besides, flyovers are proposed to avoid cross movements at junction stations.

This ‘rail-road-water pipeline and infrastructure corridor’ in Meramundali-Angul-Talcher-Chhendipada belt is projected to handle 113 million tonne coal by 2014-15. It includes 55 million tonne coal movement required by the power companies, 40.76 million tonne by steel companies and 17.22 million tonne by other industries.

Infrastructure hurdles getting noticed; Some Odisha projects in focus

Aluminium, Anil Agarwal, Bauxite, Business Standard, CENTER & ODISHA, Haridaspur - Paradeep (under constr.), Kalahandi, Talcher - Bimlagarh (under constr.), Vedanta 6 Comments »

In the following excerpts from a report in Business Standard Haridaspur-Paradip and Talcher-Bimlagarh are listed as strategic projects. I hope they are fast tracked.

… Delays in land acquisition and forest clearances continue to stand in the way of completing strategic projects like the 82-km Haridaspur-Paradip line and the 154-km link between Talcher and Bimlagarh, both in Orissa. While the first project is to give good port access to units in the steel hub of Kalinganagar, the second is designed to step up evacuation of coal from mines at Angul and Talcher.

…This is why India, endowed with the world’s fifth largest bauxite deposits and the fourth largest coal reserves, has emerged as a preferred place for making aluminium. Within the country, Orissa is where every aluminium maker wants a presence. That is why the Vedanta group, in spite of being solidly anchored in Chhattisgarh, thanks to its 50 per cent ownership of Balco, with capacity of 345,000 tonnes and then giving shape to a 650,000-tonne smelter there, wants to create alumina capacity of five mt and smelting capacity of 1.6 mt in Orissa, with adequate upstream integration in bauxite mining and coal-based power.

NAY SAYERS
Unfortunately, Vedanta is not able to realise what it has set out to do in Orissa, as it fell foul of pressure groups such as Amnesty International and Survival International and also of the ministry of environment and forests. The Niyamgiri Hills, from where Vedanta’s refinery is to draw bauxite, is considered sacred by Dongria Kondh tribesmen. But why should the company be stopped to take out bauxite from there if it is ready to resettle the displaced people and practise environment-friendly mining?

As a result of the impasse, Vedanta is required to source bauxite from outside, totally upsetting the considerations for hosting a refinery at nearby Lanjigarh. The denial of mining at Niyamgiri is setting a bad precedent for the mining sector. Redemption for Vedanta would hopefully come, with the Orissa government committed to offering alternative bauxite deposits.

There are some recent news on Vedanta’s expansion in Lanjigarh. But the news are confusing. Following is an excerpt from a September 17th report in Times of India.

Vedanta has suffered another setback in its fight-back to expand the aluminium refinery in Orissa after the Union environment ministry had struck down its environment clearance for violations.

The Cuttack bench of the Orissa High Court backed the environment ministry and ordered that Vedanta would have to apply afresh for a clearance for expansion if it wants to.

Following is an excerpt from a September 19th report in ndtv.com.

The ministry of environment and forests has cleared Vedanta Aluminium’s project in Lanjigarh, Orissa. 

The expansion of Anil Agarwal-led Vedanta Aluminium’s four million tonne Lanjigarh refinery plant in Kalahandi had been put on hold by the Union Environment Ministry  on October 21, 2010.

… Environment ministry’s expert appraisal committee (EAC) has cleared the project with 70 conditions, sources told NDTV. Major conditions among them are:  Five per cent of the total project cost would be spent on social welfare projects.The company will maintain air, water quality & develop 164 hectare of plant area as green belt.

Others conditions say that the company will also submit rehabilitation and resettlement policy covering tribals, which should be in line with government policies. The company will also be required to submit corporate environment policy approved by its board.

Land acquisition status for various railway projects; first goods train run on the Bhadrak-Dhamara line; passenger services demanded

Angul - Talcher - Sukinda (under constr.), Bhadrakh - Dhamara (port conn. planned), Haridaspur - Paradeep (under constr.), Khurda Rd - Balangir (under constr.), Talcher - Bimlagarh (under constr.) Comments Off on Land acquisition status for various railway projects; first goods train run on the Bhadrak-Dhamara line; passenger services demanded

The following is from Dharitri.

The following is from Samaja.

Odisha related ECOR and SER new lines allocations for 2011-12 and spending during 2010-11

Angul - Talcher - Sukinda (under constr.), Haridaspur - Paradeep (under constr.), Jaleshwar-Digha, Khurda Rd - Balangir (under constr.), Lanjigarh Rd - Junagarh, New Lines, Railway Budget 2010, Railway Budget 2011, Talcher - Bimlagarh (under constr.) 6 Comments »

The above can be obtained by looking at the appropriate pages of this year’s pink book and last year’s pink book. Following are images cut from both.

From 2011-12 Pink book

Following are some observations based on the above:

  1. Khurda Rd-Balangir: It seems 115.8 crores is expected to be spent on Khurda-Balangir line during March 2010-March 2011. This is close to the 120 crores that was allocated in the 2010-11 budget. So I am not sure why the budget was slashed to 60 crores. My guess is that last year they spent the money in building on the land they had already acquired. Now they need to acquire more new land to build and so until enough new land is acquired a lot of money could not be allocated for construction. The blame here lies with the railways for not anticipating in advance and not buying enough land in the previous years. The Odisha government should have also monitored this and prodded ECOR to buy enough land in advance. A bit of good news is that the budget speech explicitly mentions that Khurda Rd-Begunia will be completed this year.
  2. Talcher-Bimlagarh: Last year the allocation was 50 crores. However, it is anticipated that 99.4-37.98= 61.42 crores will be spent on this during March 2010-March 2011. For the 2011-12 the allocation is 66 crores, and the budget speech explicitly mentions that some part of this line will be completed this year.
  3. Angul – Sukinda: In 2010-11 the allocation was 22.5 crores, out of which only 12.7 crores is expected to be spent during March 2010-March 2011. For the 2011-12 the allocation is a substantial one consisting of 27 crores (RVN) plus 169.15 crores (PPP). It is not clear where the PPP money is coming from. If it is from the Odisha government or Odisha industries then railways should not take credit for it.
  4. Haridaspur – Paradeep: In 2010-11 the allocation was 101 crores, out of which 79.6 cores (=251.2-171.6 ) is expected to be spent during March 2010-March 2011. For the 2011-12 the allocation is a substantial one consisting of 10 crores (RVN) plus 169.15 crores (PPP). It is not clear where the PPP money is coming from. If it is from the Odisha government or Odisha industries then railways should not take credit for it.
  5. Daitari – Banspani: I am not sure what the deal here is. This line is supposed to be complete. I don’t know why there is a 70 crores budget for this.
  6. Lanjigarh Rd – Junagarh: This line has an allocation of 10 crores and will be completed this year. Once that is done  Ispat Express should be extended to Lanjigarh Rd or Bhawnipatna and a Bhawniaptana – Bhubaneswar express should be introduced.

Now let us move to SER.

  1. Jaleswar – Digha (41 kms): Last year 20 crores were allocated to it. But only 2 crores is expected to be spent during March 2010-March 2011. For the 2011-12 the allocation is a substantial one consisting of 150 crores. Also due to some modification in the plan the overall estimated cost has gone up from 255.11 crores to 533.63 crores. The modification includes a segment in West Bengal. It is not clear how much of the allocated 150 crores will be spent in the Odisha part and how much in the newly tagged on West Bengal part.

The overall new lines budget for 2011-12 is 733.4 crores. But if one takes out the PPP part then it is only 393 crores. And then, if the Jaleswar-Digha part is West Bengal centric and one takes 150 crores for it out then the total reduces to only 243 crores. Is Mamata Banerjee hoodwinking Odisha here?

See http://www.orissalinks.com/orissagrowth/archives/3272 for how it compares with previous years budgets. See http://www.orissalinks.com/orissagrowth/archives/4638 for a tabular listing of the new line budget over the years. See http://www.orissalinks.com/orissagrowth/archives/3202 for an old projection to the future.

2011 Updating of the Status of new railway line projects in Odisha; a projection to the future

Angul - Talcher - Sukinda (under constr.), Haridaspur - Paradeep (under constr.), Khurda Rd - Balangir (under constr.), Lanjigarh Rd - Junagarh, Naupada - Gunupur (Gauge conversion), New Lines, Railway Budget 2011, Talcher - Bimlagarh (under constr.) 4 Comments »
New Lines 2006- 07 2007- 08 2008- 09
2009- 10
2010- 11 2011 -12 Spent until 2009- 10 Spent until 2010 -11 Remai ning
Total

Khurda- Balangir

(289 kms)

23 20 32.34 28.07 120 60 105.8 211.7 474.2 428.3 700 Cap

Talcher- Bimlagarh

(154 kms)

10 15 10 10 50 66 37.98 99.4 722.8 645.4 810.8 Cap

Haridas pur- Paradip

(82 kms)

44 20 80 70 101 RVN 10 RVN 169.2 PPP

21.9 Cap

171.61 RVN

21.9 Cap 251.2 RVN 299.83 RVN 541.91 RVN 5.85 PPP

21.9 Cap

572.4 RVN 803.1 RVN 175 PPP

Angul- Sukinda Rd

(98.7 kms)

20   60 75 22.5 RVN 27 RVN 169.2 PPP

20.88 Cap

13.5 RVN

20.88 Cap 

26.2 RVN

581.62 RVN

389.4 RVN

5.85 PPP

20.88 Cap

617.6 RVN

442.6 RVN

175 PPP

Lanjigarh Rd – Junagarh

(56 kms)

19 12 35 30 60 10 169.31 176.6

0.69

1.5

170 cap

188.1 cap

Daitari – Bansa pani

(155 kms)

155.6   20 60 75 RVN 70 RVN

367 cap

671.85 RVN

367 cap

587.8 RVN

186.56 RVN

301.7 RVN

367 Cap

933.4 RVN

959.5 RVN

Jaleswar- Digha

(41 kms)

    Did not exist Did not exist 20 (new)  150 Did not exist  2 235.11 381.6

255.1 Cap

533.6 Cap

Buramara – Chakulia

with upgrad ation  of Rupsa – Buramara

(125 kms)

        under progress as an RVNL SPV.         466.5 RVN

Gunupur- Theruvali (79 kms)

(Naupada  – Gunupur 90 kms gauge conver  sion is now complete)

N-G 34 N-G 25    

Already surveyed.

But listed as a soc. desirable project. 

Odsiha should push hard for this to be designa ted as a port conn. (to Gopalpur port) project and taken up via RVN SPV.

      Odisha govt. has also indicated to push this as a PPP project.  
Total allocation on new lines (NL) and gauge conver sion (GC)

Rupsa – B 15.9

Other – 4.1

Total – 325.6 crores

Rupsa – B 35

other – 5

Total – 132 crores

244.34 + 65 = 309.34 275.07+ 36.14 = 311.21

ECOR NL – 428.7

ECOR GC – 5

SER NL – 20

SER GC – 1

Total = 454.7

ECOR NL – 583.4

ECOR GC – 12

SER NL- 150

SER GC – 2

Total= 747.4

 

2004 – 199 crores

 


     
New Lines 2006 – 07 2007- 08 2008- 09 2009- 10 2010- 11 2011- 12 Spent until 2009 -10 Spent until 2010 – 11 Remain ing Total

 

 

 

 

 

The positives of BPUT operations happening in Rourkela

Bhubaneswar- Cuttack- Puri, Khordha, Rourkela, Rourkela- Kansbahal, Sundergarh, Talcher - Bimlagarh (under constr.) 3 Comments »

With more and more BPUT operations moving to Rourkela (thanks to http://rourkelacity.com for the pointer) there could be some huge positives, but not one that people normally think as BPUT’s academic programs in Rourkela will not be better than the programs at NIT Rourkela. But there would be definitely more seats; so that would be good. But the biggest positives would be with respect to connectivity.

In particular, the connectivity between Rourkela and the rest of Odisha, especially the Bhubaneswar area, would improve. Currently not enough attention is being paid to that.

For example, the Talcher-Bimlagarh line will significantly shorten the distance between Bhubaneswar and Rourkela. The distance between them will become 308 kms: BBS-Talcher (114) + Talcher-Bimlagarh(154) + Bimlagarh-Rourkela(40). Currently the shortest distance is 419 kms. Once Talcher-Bimlagarh line is completed one could travel between BBS and ROU in about 5 hours. That would mean one could take a train from one place at 6 and reach the other at 11. Currently the BBS-ROU intercity takes 7hrs 30 minutes one way and 7hs 55 minutes the other way. On the other hand the BBS-SBP takes between 4:40 to 4:50 minutes in the two intercities (BBS-BLGR and SBP-Puri).

So lets hope that the inconvenience caused by having many BPUT operations from Rourkela will lead to people demanding speeding up of the completion of the Talcher-Bimlagarh line and perhaps even the start of shuttle flights between Bhubaneswar and Rourkela.

Another positive would be that more private colleges (not now but in few years when the demand picks up again) may come up close to Rourkela and the frequent travel by college heads to Rourkela could give them ideas to develop the travel corridor in many ways.

So although the convenience argument is often used by many (including me) to support some BPUT operations in Bhubaneswar, where most of the BPUT colleges are, perhaps for the greater and longer term good some inconvenience in the short term can be accepted.

Bringing Rourkela and Bhubaneswar closer (in travel time as well as in people’s mind) would be a big plus for Odisha.

Lets work on operationalizing Talcher-Bimlagarh line in 3-5 years!

Status of new railway line projects in Odisha; a projection to the future

Angul - Talcher - Sukinda (under constr.), Buramara - Chakulia, Haridaspur - Paradeep (under constr.), Jaleshwar-Digha, Khurda Rd - Balangir (under constr.), Lanjigarh Rd - Junagarh, Railway Budget 2008, Railway Budget 2009, Railway Budget 2010, Railway Budgets, RVNL, Talcher - Bimlagarh (under constr.), Tomka - Jaroli 8 Comments »
New Lines 2006- 07 2007- 08 2008- 09
2009- 10
2010- 11 Spent until 2009- 10 Remai ning
Total

Khurda- Balangir

(289 kms)

23 20 32.34 28.07 120 105.8 474.2 700 Cap

Talcher- Bimlagarh

(154 kms)

10 15 10 10 50 37.98 722.8 810.8 Cap

Haridas pur- Paradip

(82 kms)

44 20 80 70 101 RVN

21.9 Cap

171.61 RVN

299.83 RVN

21.9 Cap

572.4 RVN

Angul- Sukinda Rd

(98.7 kms)

20   60 75 22.5 RVN

20.88 Cap

13.5 RVN

581.62 RVN

20.88 Cap

617.6 RVN

Lanjigarh Rd – Junagarh

(56 kms)

19 12 35 30 60 169.31 0.69 170 cap

Daitari – Bansa pani

(155 kms)

155.6   20 60 75 RVN

367 cap

671.85 RVN

186.56 RVN

367 Cap

933.4 RVN

Jaleswar- Digha

(41 kms)

    Did not exist Did not exist 20 (new) Did not exist 235.11 255.1 Cap

Buramara – Chakulia

with upgrad ation  of Rupsa – Buramara

(125 kms)

        under progress as an RVNL SPV.     466.5 RVN

Gunupur- Theruvali (79 kms)

(Naupada  – Gunupur 90 kms gauge conver  sion is now complete)

N-G 34 N-G 25    

Already surveyed.

But listed as a soc. desirable project. 

Odsiha should push hard for this to be designa ted as a port conn. (to Gopalpur port) project and taken up via RVN SPV.

  Odisha govt. has also indicated to push this as a PPP project.  
Total allocation on new lines (NL) and gauge conver sion (GC)

Rupsa – B 15.9

Other – 4.1

Total – 325.6 crores

Rupsa – B 35

other – 5

Total – 132 crores

244.34 + 65 = 309.34 275.07+ 36.14 = 311.21

ECOR NL – 428.7

ECOR GC – 5

SER NL – 20

SER GC – 1

Total = 454.7

2004 – 199 crores

 


   
New Lines 2006 – 07 2007- 08 2008- 09 2009- 10 2010- 11 Spent until 2009- 10 Remain ing Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(All numbers above are in Crores of Rupees. Cap means Capital expenditure and RVN means expenditure through Rail Vikas Nigam.)

2006 had a big allocation of 155.6 crores just for Daitari-Bansapani for its completion. With that done, in 2007 Lalu really screwed [pardon my language!] Odisha with respect to the new lines by having a total budget on new lines and gauge conversion of only 132 crores. (There may have been another 20 crores in that budget in the green book.) Things picked up a bit in 2008 and 2009 and finally now, it is at a decent state.

Now we must make sure that by next year there is approval of Buramra-Chakulia and increase in the allocation for all the other projects that are not completed or about to be completed. A sample projected budget (for new lines) that we should aim for the next seven years is as follows.

  This Yr Remai ning 2011- 12 2012- 13 2013- 14 2014- 15 2015- 16 2016- 17 2017- 18
Khurda – Balangir 120 474.2 130 130 140 100 Done Done Done Done
Talcher – Bimlagarh 50 722.8 100 120 130 140 150 100 Done Done
Haridaspur – Paradip 101 300 100 100 100 Done Done Done Done Done
Angul – Sukinda 22.5 582 40 60 80 100 120 150 50  Done
Daitari – Bansapani 75 187 75 85 20  Done Done Done Done Done
Jaleswar – Digha NEW     20 235 30 30 30 60 80  Done Done Done
Buramara – Chakulia 0 467 NEW 20 50 50 120 120

120

Done

Done
Gunupur – Theruvali 0 450 (est) 0

NEW

20

50 50 100 120 120 Done
Other new lines: Puri Konark; Nabrangpur-Jeypore; Nabrangpur-Junagarh; Jeypore – Malkangiri; Malkangiri – Bhadrachal am

Lanjigarh Junagarh 60

Done

  0 0 NEW1 (1) 20  NEW2 (1) 40  (2) 20 NEW3 (1) 40 (2) 30 (3) 20 NEW4 (1) 60 (2) 60 (3) 40 (4) 20 NEW5 (1)140 (2)130 (3)120 (4) 90 (5) 20
Total 455   495 595 620 630 650 670 670

Other lines that are mentioned in the 2010-11 budget and to be pursued beyond are: Lanjigarh Rd – Phulbani – Talcher, Berhampur – Phulbani, etc.

Will Indian Railways listen to the planning commission?

Khurda Rd - Balangir (under constr.), Talcher - Bimlagarh (under constr.) Comments Off on Will Indian Railways listen to the planning commission?

Following is an excerpt from an article in Indian Express.

Prime Minister Manmohan Singh has, gently, turned the heat on absentee Railway Minister Mamata Banerjee, asking her for a status report on the Railways in a fortnight.

 Forwarding a note by Planning Commission Deputy Chairman Montek Singh Ahluwalia on an assessment of the problems at Indian Railways and suggestions for a turnaround, Singh’s attempt seems to be two-fold: one, to prod Banerjee to give time to her Ministry and two, to get things moving in the Railways, so crucial to the country’s double-digit growth ambitions. …

Drawing a parallel with China, the Plan panel said that between 1990 and 2007, Indian Railways added only about 960 km while China added 20,000 km. China plans to add another 40,000 km in the next 10 years while India is currently doing around 250-300 km a year. “There can be no doubt that we should aim at adding 1,000 km a year for the next 10-12 years totaling 10,000 km of additional route length,” it said.

I hope Indian Railways figures out a way to add 10,000 kms of additional route length during the next 10 years. That would increase the chances of long languishing projects like the Khurda-Balangir line and the Talcher-Bimlagarh line being completed within that time.

Land acquisition status of Talcher-Bimlagarh, Haridaspur-Paradip and Angul-Sukinda lines: Dharitri

Angul - Talcher - Sukinda (under constr.), Haridaspur - Paradeep (under constr.), Talcher - Bimlagarh (under constr.) Comments Off on Land acquisition status of Talcher-Bimlagarh, Haridaspur-Paradip and Angul-Sukinda lines: Dharitri

Open letter to the Prime Minister

Angul, APPEAL to readers, Balangir, Bouda, Gajapati, Kalahandi, Kandhamala, KBK Plus district cluster, Khordha, Khurda Rd - Balangir (under constr.), Koraput, Lanjigarh Rd - Junagarh, Malkangiri, Nabarangpur, Nayagarha, Sambalpur, Talcher - Bimlagarh (under constr.) 9 Comments »

"Dr. Manmohan Singh" <pmosb@pmo.nic.in>, "Chief Minister" <cmo@ori.nic.in>, "Orissa Governor" <govori@ori.nic.in>,
<abhijit.sen@yojana.nic.in>, <anwarul.hoda@yojana.nic.in>, <b.mungekar@yojana.nic.in>, <dch@yojana.nic.in>, <kirit.parikh@yojana.nic.in>, <mvraja@yojana.nic.in>, <plancom@nic.in>, <s.hameed@yojana.nic.in>, <vl.chopra@yojana.nic.in>, <yugandhar.bn@nic.in>, "subas@nic.in" <subas@nic.in>

cc to journalists: <abcxy123@hotmail.com>, <admin@dailypratap.com>, <akb@businessstandard.com>, <alokmehta7@hotmail.com>, <ankur@jaintv.com>, <arindam.sengupta@timesgroup.com>, <colpnk@hotmail.com>, <dr.jain@jaintv.com>, <editet@timesgroup.com>, <editor@deccanmail.com>, <editor@the-week.com>, <feedback@tehelka.com>, <ie.pksahoo@gmail.com>, <indinon@vsnl.in>, <karanthapar@itvindia.net>, <klnandan@yahoo.com>, <letters@deccanherald.co.in>, <letters@tribuneindia.com>, <lngoel@zeenetwork.com>, <mashriq@vsnl.net>, <mnutan@hotmail.com>, <mythilib@gmail.com>, <npnawani@indiatimes.com>, <nsuri@milap.com>, <pjoshi@hindustantimes.com>, <prabhu@intoday.com>, <punit.jain@timesgroup.com>, <punjabidigest@hotmail.com>, <pvohra@hindustantimes.com>, <rajc@intoday.com>, <ratnam@intoday.com>, <saeednaqvi@hotmail.com>, <sargamstudio@rediffmail.com>, <shishir.joshi@aajtak.com>, <takhatram@hotmail.com>, <tarunvijay@vsnl.com>, <thehindu@vsnl.com>, <toieditorial@timesgroup.com>, <ttedit@abpmail.com>, <vmehta@outlookindia.com>, <vsanghvi@hindustantimes.com>, "braja k mishra" <brajakmishra@gmail.com>, "manorama" <maya@mitraprakashan.com>, "Prasanta Kumar Sahoo" <pksahoo2002@gmail.com>, "Shishir Bhate" <shishirb@rediff.co.in>

cc to Orissa NDA mps: <ananta@sansad.nic.in>, <bmahtab@sansad.nic.in>, <deobk@sansad.nic.in>, <dharmendra@deogarhorissa.com>, <jualoram@sansad.nic.in>, <makswain@sansad.nic.in>, <mayfair@sansad.nic.in>, <pmajhi@sansad.nic.in>, <pyarimohan@yahoo.co.uk>, <pyarimohanap@sansad.nic.in>, <rknayak@sansad.nic.in>, <rn.pany@sansad.nic.in>, <surendra@sansad.nic.in>, "B J Panda" <office.bjpanda@gmail.com>, "Balbir Punj" <punjbk@gmail.com>, "jual oram" <jualoram@hotmail.com>, "Tathagata Satpathy" <tatzaudi@yahoo.com>

cc to Orissa opposition biggies: "janardan pati" <j_pati_orissa@yahoo.com>, "rohit pujari" <rohit_pujari2001@yahoo.com>, "Srikant Jena" <srikant_jena@hotmail.com>, "Chandrasekhar Sahu’s OSD" <skpattanayak@hotmail.com>

cc to BJP bigwigs: <advanilk@sansad.nic.in>, <ananta@sansad.nic.in>, <asahu@nic.in>, <ashourie@sansad.nic.in>, <bjpco@bjp.org>, <bjpco@del3.vsnl.net.in>, <bpapte@vsnl.com>, <chandan.mitra@sansad.nic.in>, <covdnhrc@nic.in>, <deobk@sansad.nic.in>, <gandhim@sansad.nic.in>, <george@sansad.nic.in>, <iisatwal@hotmail.com>, <jaswant@sansad.nic.in>, <jualoram@sansad.nic.in>, <kjana@sansad.nic.in>, <makswain@sansad.nic.in>, <minister@mit.gov.in>, <mnaqvi@sansad.nic.in>, <mprasad@nic.in>, <msgill@sansad.nic.in>, <murli@sansad.nic.in>, <mvnaidu@sansad.nic.in>, <najmah@sansad.nic.in>, <pati@nic.in>, <pilania.g@sansad.nic.in>, <pmajhi@sansad.nic.in>, <rajnath@sansad.nic.in>, <rn.pany@sansad.nic.in>, <spokesman_rss@yahoo.com>, <surendra@sansad.nic.in>, <swaraj@sansad.nic.in>, <vajpayee@sansad.nic.in>, <ysinha@sansad.nic.in>

cc to UPA bigwigs: <10janpath@vsnl.net>, <ambika_aicc@yahoo.com>, <arjuns@sansad.nic.in>, <chavanprithviraj@sansad.nic.in>, <cpim@vsnl.com>, <jairam@vsnl.com>, <kapilsibal@hotmail.com>, <km.sahni@nic.in>, <nath@sansad.nic.in>, <oscar@sansad.nic.in>, <praful@sansad.nic.in>, <sjaipal@sansad.nic.in>, <speakerloksabha@sansad.nic.in>, <svpatil@sansad.nic.in>, "Dr. Manmohan Singh" <pmosb@pmo.nic.in>, "Jairam Ramesh" <jairam@sansad.nic.in>, "Kamal Nath" <cim@nic.in>, "Ram Vilas Paswan" <psmin.cpc@sb.nic.in>

 FAX: PMO at 23016857 , 23015603 (Delhi STD code is 11), CMO at 674 2590 833 (home) 674 2535 100 (office) and Planning Commission at 23096699


 

To:

Dr. Manmohan Singh

Prime Minister of India

Cc: Mr. Naveen Patniak, Chief Minister of Orissa

Cc: Shri Muralidhar Chandrakant Bhandare, Governor of Orissa

 
Subject: Solving the greater Kandhamala problem – going after the root cause in a war footing

 

Dear Dr. Singh: 

While the civil society in Orissa, the nation and the world is disturbed by the  communal violence in Kandhamala, I would urge you to take steps to eradicate the root cause of the violence in Kandhamala and the nearby tribal, hilly, forested, awfully connected, poor and backward districts of Orissa (and its neighboring states). In this regard, please note that the violence did not spread to the major towns and cities of Orissa (such as Bhubaneswar, Puri, Cuttack, Rourkela, Sambalpur, Berhampur, Balasore etc.)  that are well connected (by Rail and roads), decently developed and have a civil society. 

While the violence involving the murder of Swami Laxmanananda on August 23rd 2008 and the subsequent communal violence that has taken about 40 lives is most deplorable and is in the forefront of the media, please also recall the following events that also took place within the last year in these areas:

 

  1. February 15 2008:  400 to 500 armed Naxals raided the Nayagarh armory and killed 15 people including 13 policemen.
  2. June 29 2008: 30 elite anti-insurgency policemen were killed by Maoists near Malkangiri.
  3. July 16 2008:  21 Orissa policemen were killed in a land mine explosion and firing by the ultras in Malkangiri.
  4. Dec 27 2007: Eleven churches were ransacked and torched in several areas of Kandhamal district.

Please note that these events happened in places in Orissa (Nayagarh, Malkangiri and Kandhamal) that are badly connected, near or within forests, have a large tribal population, and are among the most backward districts of India. The following map shows these districts are surrounded by large tracts of dense and open forested areas, and partly explains why the naxalites and Maoists are able to make them their base and why it has been difficult to deploy adequate police there in a timely manner.

(NOTE: Phulbani is now called Kandhamala)

(Note: The lines in red are the ones that are needed to bring rail connectivity to the Kandhamala, Nayagarh and Malkangiri districts and criss-cross the big connectivity gap in the heart of Orissa. The crossed segments are already approved but progressing very slowly.)

 

Sir: As an economist and a world leader you must know that lack of connectivity, lack of development, lack of a civil society, entrenched forest and mountainous areas together with a different population base is a recipe for the sprouting of troubled areas. This is true all across the world; from J& K and North eastern areas of India to caucuses in Asia. While one cannot and should not get rid of the mountains or the people, the problem can be solved by making the areas well connected and bringing development. The Indian government is doing that in J & K and in the northeast; but has mostly forgotten about the similar areas in Orissa, Chhatisgrah, and Andhra Pradesh, which are the favorite bases of the Naxals and Maoists.

Sir: We would like you to pay the same attention to these areas in terms of connectivity, development, and creation of civil societies, as you do to the North east and J & K. In particular we would request that following be done in a war footing during the 11th plan.

(i)                  The Vijaywada-Ranchi highway that passes through many of these areas be completed.

(ii)                Broadband connectivity be brought to these districts with adequate access locations.

(iii)                Two Railway lines, parts of which have already been sanctioned by the Railways but are progressing slowly, are completed and made operational. Those lines are:

a.       Khurda Rd – Balangir (passes through Nayagarh and Boudh) – This line was sanctioned in 1994-95 is progressing very slowly.

b.      Bhadrachalam Rd (Andhra Pradesh) – Malkangiri – Jeypore – Nabarangpur – Junagarh – Lanjigarh Rdpassing through Kandhamala – Boudh – Angul – Talcher – Bimlagarh: Several segments of these lines are approved but progressing slowly. Those segments are Junagarh – Lanjigarh Rd and Talcher – Bimlagarh. Angul – Talcher is operational.

(iv)              With the above lines operational, development should be brought into Kandhamal, Boudh, Gajapati, and KBK districts (including Kalahandi and Malkangiri) through 1-2 Rail factories and public sector units that can use the steel and aluminum and power produced in abundance in Orissa.

(v)                Orissa govt. should be encouraged and aided to establish a university in Kandhamala and another in Kalahandi.

(vi)              A branch of the Indira Gandhi National Tribal University be established in one of these districts.

(vii)             Orissa govt. should be encouraged and aided to establish a government medical college and nursing college in Kandhamala or Boudha district.

Sir:  In regards to the cost of establishing the Railway lines, please note that as per the calculation in  http://kbkrail.orissalinks.com/ Indian Railways is scheduled to make a profit of 2679.72 crores/year from its operations in Orissa. If 1500 crores of this money (the rest may go to Indian Railway’s current plans for Orissa) is put into Orissa, in just 2-3 years the above mentioned lines could be completed.

Sir: We sincerely hope that you will translate the great concern you have shown towards the recent violent events to the above mentioned action items that address the key issues of lack of connectivity and development in these areas and thus provide a long term and real solution.

Sincerely

 

Appendix:

1. Estimated profit Indian Railways will make from Orissa in 2008-09:

Zone in Orissa

Total Route Kms

Route kms in Orissa

Estimated

2008-2009 profit (in crores)

Orissa’s proportional share of the profit in 2008-2009

ECOR

2430

1607

3077.15

(next page)

2034.97 crores

SECR

1599

51

2529.89

(next page)

80.69 crores

SER

2577

589

2467.88

(next page)

564.06 crores

Total

 

2247

 

2679.72 crores

 

2.  One of the earlier planning commissions has noted in http://planningcommission.nic.in/plans/stateplan/sdr_orissa/sdr_orich2.doc

“Railways have always played an important role in economic development and rapid social transformation in all parts of the globe. It is one of the key economic infrastructures. However, it is most unfortunate that in a poor and backward state like Orissa, development of rail networks has received much less attention of the Central Government in the post-independence period. There are as many as seven districts like Boudh, Kandhamal, Deogarh, Nayagarh, Kendrapara, Malkangiri and Nabarangpur out of the 30 districts of the state, which do not have any railway line passing through them. In the year 1998-99, the density of railway route length per 1000 sq. km of area in Orissa was only 15.03 km as against 42.66 km in West Bengal and 19.11 km. at all-India level”.


3. The tribal population percentage of the KBK districts are as follows:  Malkangiri  58.36% ST  (+19.96% SC),  Rayagada 56.04% ST  (+14.28% SC),  Nabarangpur 55.27% ST (+15.09% SC), Koraput 50.67% ST (+13.41% SC), Nuapada 35.95%  ST(+13.09% SC), Kalahandi 28.88% ST (+17.01% SC), Sonepur 22.11% ST (+9.5% SC), Balangir 22.06% ST (+15.39% SC). Two adjacent districts also have high tribal population. They are Kandhamala 51.51% ST (+18.21% SC) and Gajapati 47.88%  ST(+8.77% SC). 

 

4. The literacy rates in the KBK districts are abysmally low. Malkangiri 31.26%, Nabarangpur 34.26%, Rayagada 35.61%, Koraput 36.2%, Nuapada 42.29%, Kalahandi 46.2%, Balangir 54.93%, Sonepur 64.07%. Two adjacent districts also have low literacy: Gajapati 41.73% and Kandhamala 52.95%. The state average is 63.1%.

5. Population below the poverty line in southern Orissa (of which KBK is a part) is reported to be 89.17% of the people according to the 1999-2000 NSS data and 72% of the families according to the 1997 census.

Uncetainty over construction of Talcher Bimalagarh Railway Line

Talcher - Bimlagarh (under constr.) Comments Off on Uncetainty over construction of Talcher Bimalagarh Railway Line

Pragativadi reported that land acquisition for Talcher Bimalagarh railway line is delaying the project.

ECOR map dated April 1 2007

Angul - Talcher - Sukinda (under constr.), Bhadrakh - Dhamara (port conn. planned), Bhadrakh-Sarla Rd...Vizag, Cuttack - Paradeep, ECOR, Haridaspur - Paradeep (under constr.), Jakhapura - Daitari, Khurda Rd - Balangir (under constr.), Khurda Rd - Puri, Koraput - Rayagada, Lanjigarh Rd - Junagarh, MAPs, Naupada - Gunupur (Gauge conversion), Overall Odisha, Railway maps, Raipur..Khariar Rd - Rayagada - Ladda..Vijainagaram, Rajathagara - Nergundi, Sambalpur - Talcher, SER, Talcher - Barang, Talcher - Bimlagarh (under constr.), Titlagarh - Jharsugurha Jn, Tomka - Jaroli, Vizag ..Shimiliguda - Koraput - Dhanapur ..Kirandul 1 Comment »

Press release on House Committee of Orissa Legislative Assembly meeting the Rail minister

Angul - Talcher - Sukinda (under constr.), Haridaspur - Paradeep (under constr.), Jakhapura - Daitari, Khurda Rd - Balangir (under constr.), Lanjigarh Rd - Junagarh, Odisha Assembly, Railways, Talcher - Bimlagarh (under constr.), Tomka - Jaroli Comments Off on Press release on House Committee of Orissa Legislative Assembly meeting the Rail minister

Following is from http://rc.orissa.gov.in/writereaddata/sublinkimages/167.doc.

 

PRESS RELEASE

New Delhi,

January 30, 2008

 
 

Reg:   Submission of Memorandum by the House Committee of OLA to the Hon’ble Minister of Railways on 30.01.2008.

 

        The members of House Committee on Railways under the Chairmanship of Hon’ble Speaker, Orissa Legislative Assembly, accompanied by the Members of Parliament submitted a Memorandum to the Hon’ble Union Minister of Railways in his office chamber. In the said meeting, Chairman, Railway Board and other high officials of Ministry of Railways were present.

 

          Orissa is on the threshold of major industrial upsurge and first progressing towards rapid industrialization. The large number of MoUs have been signed with several companies for setting up Steel Plants. Similarly, MoUs have been signed for setting up Alumina Plants and Super Thermal Power Houses. Several ports are also coming up along the Orissa coast. It is expected that additional generation of traffic will be staggering 200 to 250 MTPA by 2016.

          In the background of such massive transportation requirement, the rail infrastructure require urgent strengthening and expansion.

           Hence, the committee has given a proposal for enhancement of allocation of funds for the six ongoing projects to the tune of Rs.655 crore, for electrification of two Sections for Rs.50 crore, for gauge conversion Rs.125 crore, for doubling Rs.500 crore, altogether totaling to Rs.1330 crore, in the ensuing Railway budget.

 

        2 –

 

          Hon’ble Railway Minister gave a patient hearing to the various demands raised by the House Committee and assured to look into the various proposals positively. He further assured that additional funds will be given for the projects in the execution stage for their early completion.

 

          On Puri-Konark project, Hon’ble Minister suggested that if land can be provided by the State Government, the project can immediately be taken up by the Government of India keeping in view the huge tourist potential of the area.

         

          The Committee also requested Hon’ble Minister to sanction nine new railway lines for which survey has already been completed. Hon’ble Minister assured that sanction of viable projects will be processed for approval of Planning Commission. The Committee also put forth demand for introduction of new train services, extension of selected existing services, increasing frequency of popular trains, improving quality of onboard services and amenities at the major Railway stations in the state.

 

          The Hon’ble Minister, Railways directed the Railway officials to examine the proposals given by the House Committee on Railways of OLA.

Various news reports mention some additional details. For example, New Indian Express reports that the committee asked for the following:

Lanjigarh Road-Junagarh- Rs 120 crore, Khurda Road- Balangir-Rs 150 crore, Haridaspur-Paradip-Rs 175 crore, Angul-Dubri- Sukinda Road-Rs 75 crore,Talcher-Bimalagarh-Rs 75 crore, Daitari-Banspani-Rs 60 crore.

Electrification of Kharagpur-Nimpura- Bhubaneswar and Bhubaneswar-Kottavalasa lines-Rs 50 crore, gauge conversion of Rupsa- Bangiriposi and Naupada- Gunupur lines-Rs 50 crore and Rs 75 crore respectively and doubling of Titlagarh- Lanjigarh Road-Rs 500 crore.

Orissa to fall drastically behind in Rail density

Angul - Talcher - Sukinda (under constr.), Baripada - Bangiriposi (under constr.), Bhadrakh - Dhamara (port conn. planned), ECOR, Haridaspur - Paradeep (under constr.), Khurda Rd - Balangir (under constr.), Lanjigarh Rd - Junagarh, Naupada - Gunupur (Gauge conversion), Railways, SER, Talcher - Bimlagarh (under constr.) Comments Off on Orissa to fall drastically behind in Rail density

The following is from the PIB http://pib.nic.in/release/release.asp?relid=33421. (Based on this Orissa will fall behind quite a bit: Only 2000kms of new lines
 none of the major new lines in Orissa, such as Khurda-Balangir, will get completed during the 11th plan. The states where the freight corridor will run and the states with a lot of narrow gauge lines will surge forward.)

In order to carry additional freight and passenger traffic in future, Railways have on hand 272 track capacity works, which on completion would add 20,852 kilometers to the Broad Gauge system.  The estimated throwforward cost of these works is approximately Rs. 55,000 crore.

 

A substantial amount of traffic moves on the High density routes viz. the ones which connect the four metropolitan cities of Delhi, Mumbai, Chennai, Kolkatta, and the Delhi – Gaulhati route.  Railways have already announced construction of two Dedicated Freight Corridors between JNPT-Tughlakabad (1483 kms) and Sonenagar-Ludhiana, (to be later extended to the deep sea port of Kolkatta) (1279 kms) at a cost of more than Rs. 28,000 crores to give relief to two of the densely saturated routes viz. Delhi-Mumbai and Delhi-Kolkata routes.  In addition, feasibility studies have been ordered on four other corridors – (i) North – South (Delhi-Chennai); (ii) East – West (MumbairKolkotta); (iii) South – East (VijayawadaKharagpur ) and (iv) South – South (Chennai – Goa).

In addition, Railway proposes to augment its track capacity in XI Plan by 15,500 kilometers, including 2000 kilometer of new lines, 3500 kilometers of doubling and 10,000 kilometers of gauge conversion.

The revenue earning freight traffic in the XI Five Year Plan period is expected to increase from 728 million tonnes in 2006-07 to 1100 million tonnes in 2011-12.  The corresponding freight output is expected to increase from 475 billion ton kilometers in 2006-07 (prov.) to 707 billion ton kilometers in 2011-12.  In order to cater to the projected freight traffic, it is expected that 62000 wagons would be required during the XI Plan.  Railways will also require to induct 1800 electric and 1800 diesel locomotives for carrying the projected traffic in the XI plan.  In addition to enhance the capacity of the existing diesel and electric locomotive manufacturing units, Railways are also going in for setting up a diesel locomotive factory at Marhowra and electric loco factory at Madhepura which will produce 150 and 120 locos per year respectively.

Since capacity augmentation takes time, Railways have taken immediate steps to enhance the throughput by increasing the carrying capacity of wagons by 6 tonnes on most of the routes and by 8 tonnes on selected routes and also strengthen the track, bridges and allied structures.  In addition, 28 heavy mineral routes with over 6900 route kilometers have been further identified for implementation of 25 tonne Axle load.  Also on selected routes, double stack containers trains have been permitted to further enhance the throughput per train.

Railways also plan to induct wagons of better design, higher capacity, longer life and low on maintenance.

The passenger traffic in the XI Five Year Plan is expected to increase from 6242 million passengers in 2006-07 (RE) to 8400 million in 2011-12.  The correspondence passenger output is expected to increase from 700 billion passenger kilometers to 880 billion passenger kilometers.

In order to cater to this increase in traffic, it is expected that 22500 coaches would be required  during the XI Five Year Plan,  implying a yearly requirement of 4500 coaches.  In order to meet this requirement , the production capacities of the existing units –integral Coach Factory, Prembur  and Rail Coach Factory, Kapurthanla – are being enhanced to 1500 and 1400 coaches per annum respectively from the  present capacity of 1000 coaches per annum each.  Further, a new coach factory is also being planned to be set up at Rai Bareily to bridge the shortfall in requirement and production capacities.

 

Railways have constructed a total of 4084 kilometers of track in the last three years.  The details are as under :

 

Category

New Lines

Doubling

Gauge Conversion

Total

2004-05

150

779

282

1211

2005-06

180

744

231

1155

2006-07

250

1082

386

1718

Total

580

2605

899

4084

 

This information was given by the Minister of State for Railways Shri R.Velu in written reply to a question in the Lok  Sabha today.

MP Rudra Pani raises the issue of Rail connectivity in the parliament: Pragativadi

Angul - Talcher - Sukinda (under constr.), Haridaspur - Paradeep (under constr.), Khurda Rd - Balangir (under constr.), Lanjigarh Rd - Junagarh, Odisha MPs, Railway network in Odisha, Talcher - Bimlagarh (under constr.) Comments Off on MP Rudra Pani raises the issue of Rail connectivity in the parliament: Pragativadi

Railways in North and Northwest Orissa

Angul, Angul - Talcher - Sukinda (under constr.), Balasore, Bargarh, Bhadrakh, Bouda, Deogarh, ECOR, Jakhapura - Daitari, Jharsuguda-Sambalpur- Bargarh, Jharsugurha, Keonjhar, Mayurbhanj, Railway maps, Rourkela-Jharsuguda, Sambalpur, Sambalpur - Talcher, SER, Sonepur, Sundergarh, Talcher - Bimlagarh (under constr.), Titlagarh - Jharsugurha Jn, Tomka - Jaroli Comments Off on Railways in North and Northwest Orissa

ecor-status-april1-2007-north-orissa.JPGecor-status-april1-2007-northwest-orissa.JPG