NHDP (National Highways Development Project) and Odisha

Bhubaneswar - Paradeep, Capital Region Ring Road (CRRR), Coastal highway, NH 203 (97 Kms: Bhubaneshwar-Pipili-Puri-Konark), NH 215 (348 Kms: NH-5@Panikoli - Anandapur - Kendujhargarh -Rajamundra @NH-23), NH 23 (209 Kms: Jharkhand Border - Rourkela - Rajamundra - Pala Laharha - Talcher - NH-42), NH 42 (261 Kms: NH-6@Sambalpur - Redhakhol - Anugul - Dhenkanal - NH-5@Nergundi), NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border), NH 5A (77 Kms: NH-5 at Chandikhol to Paradip), NH 6 (462 Kms: Chhattisgarh Border - Lobarchatti - Bargarh - Sambalpur - Deogarh - Kendujhargarh - Jashipur - Bangriposi - Jharkhand Border ), NH 60 (57 Kms: West Bengal Border- Jaleswar - Baleshwar), Overall Odisha, SH 10 Sambalpur - Jharsuguda - Rourkela, State highways, Vijaywada-Ranchi highway 3 Comments »

The various phases of NHDP and their meaning, as obtained from wikipedia,  is as follows:

Phase I: The Golden Quadrilateral (GQ; 5,846 km) connecting the four major cities of Delhi, Mumbai, Chennai and Kolkata.

* In Odisha: Part of the GQ connecting Kolkata to Chennai.

Phase II: North-South and East-West corridors comprising national highways connecting four extreme points of the country. The North-South and East-West Corridor (NS-EW; 7,300 km) connecting Srinagar in the north to Kanyakumari in the south, including spur from Salem to Kanyakumari (Via Coimbatore and Kochi) and Silchar in the east to Porbandar in the west.

* In Odisha None

Phase III: The government recently approved NHDP-III to upgrade 12,109 km (7,524 mi)of national highways on a Build, Operate and Transfer (BOT) basis, which takes into account high-density traffic, connectivity of state capitals via NHDP Phase I and II, and connectivity to centres of economic importance. contracts have been awarded for a 2,075 km (1,289 mi).

* In Odisha (From http://www.nhai.org/nhdpphase3.asp.)

  • Panikholi-Keonjhar- Rimoli, NH 215, 106kms
  • Duburi – Talcher, NH 200, 98kms
  • Bhubneshwar-Puri(Approved Length 59 Km) 203 67
  • Chandikhole-Duburi 200 39
  • Rimoli – Roxy – Rajamunda(Approved Length 163Km) 215 96
  • Sambalpur-Baragarh-Chattisgarh/Orrisa Border 6 88 Balance for award

Phase IV: The government is considering widening 20,000 km (12,000 mi) of highway that were not part of Phase I, II, or III. Phase IV will convert existing single lane highways into two lanes with paved shoulders. The plan will soon be presented to the government for approval.

* In Odisha (From http://www.nhai.org/ppp.htm.)

Phase V: As road traffic increases over time, a number of four lane highways will need to be upgraded/expanded to six lanes. The current plan calls for upgrade of about 5,000 km (3,100 mi) of four-lane roads, although the government has not yet identified the stretches.

* In Odisha (From http://www.nhai.org/nhdpphase5.asp.)

  • Six Laning of Chandikhol-Jagatpur-Bhubaneswar(Approved Length 61 Km) 5 67
  • Dhankuni-Balasore (Orissa portion Balasore – Laxmannath) 2 , 6& 60 235.68
  • Bhubneshwar-Ichchapuram 5 164.33
  • Balasore –Chandikhol 5 138.14

 

Phase VI: The government is working on constructing expressways that would connect major commercial and industrial townships. It has already identified 400 km (250 mi) of Vadodara (earlier Baroda)-Mumbai section that would connect to the existing Vadodara (earlier Baroda)-Ahmedabad section. The World Bank is studying this project. The project will be funded on BOT basis. The 334 km (208 mi) Expressway between ChennaiBangalore and 277 km (172 mi) Expressway between KolkataDhanbad has been identified and feasibility study and DPR contract has been awarded by NHAI.

* In Odisha: None yet.

Phase VII: This phase calls for improvements to city road networks by adding ring roads to enable easier connectivity with national highways to important cities. In addition, improvements will be made to stretches of national highways that require additional flyovers and bypasses given population and housing growth along the highways and increasing traffic. The government has not yet identified a firm investment plan for this phase.

* In Odisha: None yet.


In addition to the above some of the other major highway development activities are:

The following annotated map shows the above highways on the Odisha map.


The blue path is the divided 2 lane Vijaywada-Ranchi highway; the red one, already a 4-lane highway as part of the Golden Quadrilateral will become a 6-lane highway; and the orange (state/PPP funded) and pink (part of NHDP) ones will be 4-lane highways. I believe soon the remaining parts of NH 5 (for port connectivity to ports in Balasore district) and NH 6  (as it connects Mumbai-Kolkata) will also become 4-lane highways and all the new ports coming up will be connected to the GQ by 4-lane highways.

The concern is the bottom half of Odisha which will not have good roads except the Vijaywada-Ranchi highway. Unless particular attention is paid to that part, it will fall further behind.


The expressway plan at http://www.orissalinks.com/orissagrowth/topics/tnc-all/roads-and-highways-infrastructure-in-orissa/expressways does cover all of Odisha in phases. If parts of it can be expedited then it will help.

NHAI plans in and around Bhubaneswar; lots of new flyovers

Cuttack, Khordha, NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border) 1 Comment »

Following are excerpts from a report in Times of India.

… NHAI state project director Aditya Kumar Ray said work has started on the flyovers at Rasulgarh and Fire Station and the construction similar projects at CRPF Square, Acharya Vihar and Vani Vihar will commence soon.

Except for the Rasulgarh project, the other flyovers will be similar to the one at Jaydev Vihar. The Rasulgarh flyover will have extra slopes to facilitate seamless traffic flow from Cuttack to Puri as well as on NH-5. It will be aesthetically designed as an entrance point to Bhubaneswar, he said.

… Sources said NHAI needed to acquire more land at Rasulgarh to execute the project. "We are in the process of acquiring some more land at Rasulgarh. Everywhere else in Bhubaneswar, the expansion will happen with the land already acquired," Ray said.

NHAI plans to construct vehicular underpasses at VSS Nagar, Vani Vihar railway overbridge (ROB), Pahal, Press Chowk. The pedestrian underpasses will be built at Kali temple, CRPF Chowk, Iskon temple, OCAC building, RTO office, University Law College and Rasulgarh.

Just outside Bhubaneswar, NHAI will construct flyovers at Phulnakhara, Khapuria, Jagatpur and Manguli in Cuttack. Work for three-lane bridges over the rivers Hansapal, Kathajodi, Mahanadi and Birupa has already started. "The bridges will be hopefully ready by 2014," Ray said.

The existing two-way bridges on these rivers will be made one way and the new bridges will be used for traffic going the other way. The NHAI had signed an agreement with Sri Jagannath Expressway Pvt Ltd, a concessionaire of three private firms (SREI, Simplex and GALFAR), on August 6, 2010, for widening and redevelopment of the 67-km-long Bhubaneswar-Chandikhol section of the Kolkata-Chennai highway. The road will be constructed to sustain vehicular traffic at a speed of 100 km per hour. However, the actual speed limit will be decided by the civic administration, the NHAI official said.

The project will cost Rs 1,047 crore and NHAI will provide Rs 205 crore. The developer will generate the rest of the funds through design, build, finance, operate and transfer (DBFOT) basis. "The developer will maintain the road for 26 years,” Ray said.

Once the construction is over, the developer will collect toll from the road users. According to initial estimates, heavy vehicles will have to pay something over Rs 100 and light vehicles would be charged an amount between Rs 80 to Rs 100.

… At present, over 5,000 heavy vehicles pass through the national highway in the city every day. To reduce the traffic load within Bhubaneswar, police divert the vehicles towards Cuttack from Pitapalli via Chandaka. Sources said NHAI has plans to make a bypass road from Khurda to Tangi bypassing Cuttack and Bhubaneswar.

Land acquisition for various NH broadening to be speeded up: Dharitri

NH 200 (440 Kms: Chhattisgarh - Jharsuguda - Deogarh - Talcher - Kamakhyanagar - Duburi - Chandhikhol), NH 203 (97 Kms: Bhubaneshwar-Pipili-Puri-Konark), NH 23 (209 Kms: Jharkhand Border - Rourkela - Rajamundra - Pala Laharha - Talcher - NH-42), NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border), NH 6 (462 Kms: Chhattisgarh Border - Lobarchatti - Bargarh - Sambalpur - Deogarh - Kendujhargarh - Jashipur - Bangriposi - Jharkhand Border ) 2 Comments »

Work on five NH projects in Odisha – Bhubaneswar-Puri, Bhubaneswar-Sambalpur, Bhubaneswar-Chandikhole, Sambalpur-Bargarh and Remudi-Rajamunda (NH-215) to begin in February 2011

Angul, Bargarh, Bhubaneswar- Cuttack- Puri, Bhubaneswar-Cuttack- Kalinganagar, Bhubaneswar-Puri, Cuttack, Dhenkanal, Jajpur, Khordha, National Highways, NH 215 (348 Kms: NH-5@Panikoli - Anandapur - Kendujhargarh -Rajamundra @NH-23), NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border), Puri, Sambalpur, Sambalpur-Burla-Jharsuguda 4 Comments »

Following is an excerpt from a report in Business Standard.

The work on five major National Highway (NH) projects in the state- Bhubaneswar-Puri, Bhubaneswar-Sambalpur, Bhubaneswar-Chandikhole, Sambalpur-Bargarh and Remudi-Rajamunda (NH-215) will begin in February 2011. While work on four-laning of the Bhubaneswar-Puri NH is expected to be completed soon, the remaining projects will be commissioned within three years."The work on these NH projects will commence in February 2011 and the projects are expected to be commissioned within three years. The work is being taken up on the Public Private Partnership (PPP) mode and the cost assessment will be made by NHAI. …

While work will be taken up for four-laning of Bhubaneswar-Puri (60 km) and Sambalpur-Bargarh (88-km) NHs, the Bhubaneswar-Sambalpur and Bhubaneswar-Chandikhole (62 km) highways will be six laned. As per the thumb rule Rs 4 crore will be spent per km on building these highways.

11km bypass from Bhuasuni temple to Daya bridge to make it faster to travel between Cuttack and Puri

Bhubaneswar- Cuttack- Puri, Cuttack, Khordha, NH 203 (97 Kms: Bhubaneshwar-Pipili-Puri-Konark), NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border), Puri 2 Comments »

Following is an excerpt from a report in Telegraph.

The traffic woes of the people commuting between Rasulgarh and Samantarapur are likely to come to an end with the construction of the proposed 11km bypass road from Bhuasuni temple to Daya bridge.

Part of the 67.25km NH-203 project, the bypass road will not only provide better and faster communication facilities to the people of 11 villages from Pandra to the Daya bridge near Lingipur, but also help commuters between Cuttack and Puri avoid the congested capital. The project will be undertaken by the Bhubaneswar Expressway Pvt. Ltd, for which tenders have been finalised.

Project director of the National Highways Authority of India (NHAI), Aditya Kumar Ray said the bypass road has been proposed specifically to address the traffic problem on the stretch from Rasulgarh and Samntarapur. …

… Ray said though the work is supposed to start from January 30, land acquisition problems were likely to cause some delay and ultimately the project may kick off in the first week of February.

… The project is likely to be over in two and a half years. To be executed in the design, build, finance, operate and transfer (DBFOT) mode, the road would be handed over to the NHAI by the operators after 29 years.

Five new flyovers will allow people to zip past the busy parts of Bhubaneswar

Bhubaneswar- Cuttack- Puri, Cuttack, Khordha, NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border), Telegraph Comments Off on Five new flyovers will allow people to zip past the busy parts of Bhubaneswar

Following is an excerpt from a report in Telegraph.

Five upcoming flyovers between Baramunda and Palasuni on National Highway 16 will reduce the commuting time of the city’s passengers in the future.

The National Highways Authority of India (NHAI) has planned to construct flyovers at important junctions like Fire station, CRP Square, Acharya Vihar, Vani Vihar and Rasulgarh.

These four-lane flyovers are expected to ease traffic problems along the Kolkata-Chennai highway (NH 16).

NHAI project director Aditya Kumar Ray said here today that an agreement was signed between Sri Jagannath Expressway Pvt. Ltd and the NHAI on August 6 for redevelopment project of the 67-kilometre stretch between Bhubaneswar-Cuttack-Chandikhol. The five fly-overs are part of the project.

“The total cost of the project would be around Rs 1,250 crore and the construction period will be two and half years. Sri Jagannath Expressway Pvt. Ltd will also take care of the maintenance of the road for 26 years (including the project execution period) as per the agreement,’’ Ray said.

“While the preliminary work will begin from October, the final work will start from December. We will try to make it a point that construction work along the entire stretch finishes on time,” he said.

… “These upcoming flyovers will have controlled access to the highway. Commuters will have to take turns at the respecting connecting roads to reach their destinations. There is also a plan to include construction of new flyovers at Phulnakhara, and Link Road-Khapuria starting from Kathjodi bridge and Manguli,’’ he added.

NH 16, which was earlier NH 5, has been clubbed with NH 60 (the Lakshman Nath-Balasore highway). Gazette notification has already been made on this highway as it falls under the Golden Quadrilateral project.

According to sources, in the past there was a plan by the NHAI to construct three flyovers at Khurda, Khandagiri and Baramunda. However, only the flyover project at Baramunda was realised, while the Khandagiri flyover plan was shifted to Jayadev Vihar to meet public demand.

As mentioned in the last paragraph, currently that stretch of NH-5 (to be called NH 16) has a flyover at Jayadev Vihar and at Baramunda. With the proposed flyovers at Fire station, CRP Square, Acharya Vihar, Vani Vihar and Rasulgarh the stretch from Rasulgarh to Baramunda would be smooth sailing without any traffic stops. See http://www.telegraphindia.com/1100813/images/13zzflyoverbig.jpg for a graphics of this stretch. The flyovers at Phulnakhara, and Link Road-Khapuria would make the streatch from central Cuttack to past Bhubaneswar without any traffic stops.

Contract awarded for six laning of Bhubaneswar-Chandikhol: includes flyovers at CRP, Acharya Vihar, Vani Vihar and Rasulgarh squares in Bhubaneswar

Bhubaneswar, Bhubaneswar- Cuttack- Puri, Bhubaneswar-Cuttack- Kalinganagar, Cuttack, Cuttack, Expressways, Jajpur, Khordha, NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border) 3 Comments »

Following is from a report in Pioneer:

The six-laning work of the Bhubaneswar–Chandikhol portion of the National Highway-5 will begin from September, after this rainy season. A sum of Rs 1,047 crore will be invested for the project under the NHDP Phase-5. A consortium has been formed with three private companies, and the contract awarded, an official of NHAI said.

The consortium of Srei, Gulfar and Simplex Infrastructure would undertake the project, which is scheduled to be completed in two and a half years’ period. This would be done on the BOT basis. After completion of the work, the consortium would maintain the road and collect toll for a period of 26 years.

After the four-laning work of the NH-5, this is the first stretch within Odisha to have six lanes. The distance from Bhubaneswar to Chandikhol is 67 km, which would have seven flyovers and four major bridges over the river Kathjodi, Kuakhai, Mahanadi and Birupa. Out of the seven flyovers, four would be built over the CRP, Acharya Vihar, Vani Vihar and Rasulgarh squares along the highway in Bhubaneswar.

Various road development plans across Orissa: Dharitri

Cuttack, Jharsugurha, Khordha, NH 42 (261 Kms: NH-6@Sambalpur - Redhakhol - Anugul - Dhenkanal - NH-5@Nergundi), NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border), Sambalpur, Sundergarh, Vijaywada-Ranchi highway Comments Off on Various road development plans across Orissa: Dharitri

Six laning of Chandikhol-Jagatpur-Bhubaneshwar approved

Bhubaneswar-Cuttack- Kalinganagar, Cuttack, Jajpur, Khordha, NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border) 1 Comment »

Following is from http://pib.nic.in/release/release.asp?relid=47065.

The Cabinet Committee on Economic Affairs has approved for the six laning of following nine stretches for a total length 1409.93 km costing Rs.18238.05 crore under NHDP Phase V on DBFOT basis:

No.

Section

State

NH No.

Length

Total Project Cost including cost of LA, R&R, pre- constr. (Rs. crore)

Concession Period in-cluding construction period of 30 months

1

Delhi-Agra

UP/Haryana

2

179.10

2494.00

26 years

2

Kishangarh-Udaipur

Rajasthan

79A, 79 & 76

315

3597.47

29 years

3

Chandikhol-Jagatpur-Bhubaneshwar

Orissa

5

67.00

1104.00

27 years

4

Vijayawada-Elluru-Rajamundri

Andhra Pradesh

5

198.20

2751.15

30 years

5

Varanasi-Aurangabad

UP

2

192.40

2974.75

30 years

6

Nellore-Chilkaluripet

Andhra Pradesh

5

183.7

2433.90

30 years

7

Krishnagiri-Walahjpet

Tamil Nadu

46

148.30

1673.17

30 years

8

Belgaum-Dharwad

Karnataka

4

80.18

707.61

30 years

9

Indore-Dewas

MP

3

45.05

502.00

30 years

            The project will be developed by the NHAI through the PPP and the Concessionaire will be selected by NHAI following two stage bidding process.  The first stage of the bidding process i.e., pre-qualification of the bidders has already been completed by NHAI.  The second stage of bidding is in process.

Proposed road network in the Bhubaneswar development plan area

Bhubaneswar and vicinity, Bhubaneswar- Cuttack- Puri, Khordha, NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border), Road maps, Roads, highways and Bus stands 2 Comments »

Six-lane expressway between Bhubaneswar and Chandikhole to come up soon

Bhubaneswar- Cuttack- Puri, Bhubaneswar-Cuttack- Kalinganagar, Cuttack, Hindu, Business line, Khordha, NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border) Comments Off on Six-lane expressway between Bhubaneswar and Chandikhole to come up soon

Following is an excerpt from a report in Hindu. (See also http://www.orissalinks.com/orissagrowth/?p=526, http://www.orissalinks.com/orissagrowth/?p=480  and http://www.orissalinks.com/orissagrowth/?p=319 )

Construction companies eyeing the access controlled, six-lane expressway projects of National Highways Authority of India (NHAI) are likely to get investment opportunities for at least four such projects spread over 495 km over the next few months.

They are Chandikhol-Jagatpur-Bhubaneswar (70 kilometre length, estimated cost Rs 761 crore), Delhi-Hapur (47 km, Rs 474 crore), the 198-km stretch of Vijayawada-Elluru-Rajamundri (Rs 1,602 crore) and the 180-km stretch on Delhi-Agra highway (Rs 1,918 crore). The feasibility reports for these projects are already completed and the work is likely to be awarded in about six months, said NHAI officials. Toll collection

These projects are for widening the current four-lane highways into six lanes and operating them for certain durations.

Companies would have to bid competitively for these projects on a revenue-sharing basis. Thus companies would have to bid on the extent of toll revenue that they are ready to share with the Government if they are allowed to operate the roads.

Since these highways are already four-lane stretches, the road operators can start toll collection even during the project construction phase from an ‘appointed date’ (within six months of winning the project), mutually decided by NHAI and the road operator. The toll revenues will be routed to an escrow account.

… From the NHAI perspective, these projects have emerged as money-spinners, with companies willing to foot the entire construction cost and part with two per cent to 48.06 per cent of their revenues in the initial leg of the project.

At the end of the concession period, which is about 12 to 15 years duration, the winning firms have agreed to part with 12 per cent to 59 per cent share of toll revenues.

Tree plantation on the Bhubaneswar-Chandikhole NH-5 stretch

Bhubaneswar-Cuttack- Kalinganagar, NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border) 6 Comments »

Following is from the PIB http://pib.nic.in/release/release.asp?relid=33328.

In some stretches entrusted to National Highways Authority of India, maintenance of trees is included as a part of ongoing Operation & Maintenance contracts. The details are as under:

(i) NH-8   :           Jaipur  bypass

(ii) NH-79A: Kishangarh – Kanwaliyas-Jajaro Ka Khera section (km. 0 to km. 35) &   NH-79 (km. 15 to km. 163.90).                             

(iii)   NH-76   :    (Udaipur-Chittorgarh (km. 113.825 to km. 220.00).

(iv) NH-5      :       Bhubaneswar-Jagatpur-Chandikhole (km. 0 to km. 61).

Roads and Highways infrastructure in Orissa

Angul, Balangir, Balasore, Bargarh, Baripada-Balasore-Kirtania, Bhadrakh, Bhadrakh-Balasore, Bhadrakh-Dhamara, Bhubaneswar-Berhampur, Bhubaneswar-Cuttack- Kalinganagar, Bhubaneswar-Dhenkanal- Anugul, Bhubaneswar-Nayagarh, Bhubaneswar-Paradip, Bhubaneswar-Pipli- Astaranga, Bhubaneswar-Pipli- Konark, Bhubaneswar-Puri, Bouda, Choudwar-Kendrapara - Dhamara, Coastal highway, Corridors emanating from Bhubaneswar metro, Cuttack, Cuttack-Paradip, Deogarh, Dhenkanal, DISTRICTS & BLOCKS, Gajapati, Ganjam, Grama sadak, Jagatsinghpur, Jajpur, Jharsuguda-Sambalpur- Bargarh, Jharsugurha, Kalahandi, Kalinganagar - Kamkhya Nagar - Talcher, Kalinganagar - Panikoili - Jajpur - Kendrapara, Kalinganagar - Tarini - Keonjhar, Kalinganagar- Chandikhol- Paradip, Kalinganagar-Bhadrakh, Kandhamala, Kendrapada, Keonjhar, Khordha, Koraput, Malkangiri, Mayurbhanj, Mining Corridor, Nabarangpur, National Highways, Nayagarha, NH 200 (440 Kms: Chhattisgarh - Jharsuguda - Deogarh - Talcher - Kamakhyanagar - Duburi - Chandhikhol), NH 201 (310 Kms: Boriguma - Bhawanipatna - Balangir - Bargarh), NH 203 (97 Kms: Bhubaneshwar-Pipili-Puri-Konark), NH 203A (49 Kms: Puri - Bramhagiri - Satpada), NH 215 (348 Kms: NH-5@Panikoli - Anandapur - Kendujhargarh -Rajamundra @NH-23), NH 217 (438 Kms: Chhattisgarh Border - Khariar Rd - Nuapada - Khariar - Titlagarh - Ramapur - Baligurha - Asika - Brahmapur - Gopalpur), NH 224 (298 Kms: Khordha - Nayagarh - Dashapalla - Bauda - Sonapur - Balangir), NH 23 (209 Kms: Jharkhand Border - Rourkela - Rajamundra - Pala Laharha - Talcher - NH-42), NH 42 (261 Kms: NH-6@Sambalpur - Redhakhol - Anugul - Dhenkanal - NH-5@Nergundi), NH 43 (152 Kms: Chhattisgarh Border - Chandili - Borigma - Jaypur - Koraput - Sunki - Andhra Pradesh Border), NH 5 (488 kms: NH No.6 in Jharkhand - Baripada - Baleshwar - Bhadrakh - Cuttack - Bhubaneswar - Khordha - Brahmapur - upto Andhra Pradesh Border), NH 5A (77 Kms: NH-5 at Chandikhol to Paradip), NH 6 (462 Kms: Chhattisgarh Border - Lobarchatti - Bargarh - Sambalpur - Deogarh - Kendujhargarh - Jashipur - Bangriposi - Jharkhand Border ), NH 60 (57 Kms: West Bengal Border- Jaleswar - Baleshwar), NH 75 (18 Kms: Jharkhand Border to NH-215 near Parsora), Nuapada, Overall Odisha, Puri, Puri - Konark, Rayagada, Road maps, Roads, highways and Bus stands, Rourkela-Jharsuguda, Sambalpur, Sonepur, State highways, Sundergarh, Vijaywada-Ranchi highway Comments Off on Roads and Highways infrastructure in Orissa

 

In recent years there has been a big jump in the number of kilometers of national highways in Orissa. Following is copied from my page "Roads and Highways infrastructure in Orissa."

Road network: Orissa Roads1; Orissa Roads2; India’s NH network; India’s golden quadrilateral; the part of the GQ/NH-5 that runs through Orissa.

  • National Highways in Orissa and India; its growth in recent years:
    • NH 5: Junction with NH No.6 in Jharkhand near Baharagora-BaripadaBaleshwar-Bhadrakh-Cuttack- Bhubaneswar-Khordha-Chhatrapur-Brahmapur– upto Andhra Pradesh Border. (488 kms)
    • NH 5A: Junction with NH No.5 near Haridaspur-Paradip Port. (77 kms)
    • NH 6: From Chhattisgarh Border-Lobarchatti- BargarhSambalpur-Deogarh-Barakot- Kendujhargarh -Jashipur-Bangriposi-upto Jharkhand Border (462 kms)
    • NH 23: From Jharkhand Border-Panposh-Raurkela– Rajamundra-Barakot- Pala Laharha-Talcher-Jn. with NH-42 (209 kms)
    • NH 42: Junction with NH No.6 near Sambalpur– Redhakhol-Anugul-Dhenkanal- Jn. with NH-5 near Cuttack. (261 kms)
    • NH 43: From Chhattisgarh Border– Dhanpunji- Borigma- JaypurKoraput-Sunki- Andhra Pradesh Border. (152 kms)
    • NH 60: From West Bengal BorderJaleswarBaleshwar (57 kms)
    • NH 75: From Jharkhand Border to junction with NH No.215 near Parsora (18 kms)
    • NH 200: From Chhattisgarh-Machida-Jharsuguda– Kochinda- Deogarh –Talcher-Kamakhyanagar-Sukinda- Chandhikhol (440 kms)
    • NH 201: Boriguma-Ampani-Bhawanipatna– Belgan- Balangir-Luisinga-Jogisuruda-Dunguripali-Bargarh (310 kms)
    • NH 203: Bhubaneshwar-Pipili-PuriKonark (97 kms)
    • NH 203A: The highway starting from its junction with NH-203 at Puri, connecting Bramhagiri and terminating at Satpada (49 kms)
    • NH 215: Panikoli-Anandapur-Ghatgan- Kendujhargarh– Parsora-Koira-Rajamundra (348 kms)
    • NH 217: From Chhattisgarh Border-Nauparha-Khariar- Titlagarh-Belgan- Ramapur- Baligurha-Sorada-Asika- Brahmapur– Narendrapur- Gopalpur (438 kms)
    • NH 224: Khordha-Nayagarh-Dashapalla- Purunakatak-Bauda-Sonapur-Balangir (298 kms)
  • Vijaywada-Ranchi highway (approved by planning commission as reported in May 2006), [July 06] [The Orissa government has been demanding a NH from Vijaywada to Ranchi which will pass through the Naxal infested areas. 1200 km of this 2000km will be in Orissa. CM talked to planning comission about it.]
  • Ongoing National Highway work in Orissa
  • Future plans for Orissa: [1:april-28-05]; [2:april-28-05].
  • Various phases of NHDP: [1]; [2]; [3]
  • Other highway plans:
    • 4 laning of Chandikhol-Paradip by February-end of 2007
    • 4 laning of Keonjhar-Panikoili, Duburi-Talcher, Cuttack-Paradeep and Duburi-Keonjhar Highways. [June17-05-Pragativadi]
  • Aim-for-with-high-priority/parts-of-it-in-Orissa-govt- plan(page4)-already:
    • Connect NH 215 (perhaps at Jajpur Rd) to Jenapur to NH200 (where it meets Brahmani) with a highway as Jenapur is the location where the National waterway will cross the railway line and Jenapur is 7 kms from where a branch of the line goes to Daitari and Bansapani.
    • Designate AP-border-Koraput-Raygada-Padampur- Berhampur (in NH5) as a National highway. (This will bring Koraput and Raygada, thus a big part of KBK, closer to BBSR) — a slight revision of what is in the plan
    • Designate Anandpur (NH 215)-Bhadrak-Dhamara port as an NH. (This will bring Dhamara port closer to Jharkhand, thus helping industries in Jharkhand and Orissa.)
    • Jagatpur-Kendrapara-Chandbali-Dhamara — make it an NH (alternative route to Dhamara port)
    • Panikoili/Kuakhia-Jajpur-Aradi-Chandabali — make it an NH (alternative route to Dhamara port)
    • Panikoili-Jajpur-Kendrapara-NH5a-Paradeep — make it an NH (alternative to Paradeep port)
  • Orissa State Road Transport Company (OSRTC)
  • Wide city roads:
    • Four-laning of the Airport-Dhamana Chhaka road in Bhubaneswar: [1]
    • Other Bhubaneswar Road plans: [1], [2]
  • Bhubaneswar area road plans: